Majority
Thompson-Starrett Company contracted with the owner of certain premises for the dismantling of the buildings standing thereupon, and the erection of a department store in their place. It subcontracted with Ottomar Stange and Anna A. Stange, composing the firm of Stange Construction Company, for the performance of a substantial portion of the work. This included all dismantling, all excavating, the building of foundation walls, the laying of all concrete below the under side of the first floor level, and various other items. The contract provided: “ The sum to be paid by Contractor to Sub-Contractor for the work shall be Four Hundred Thirty-two Thousand and No/100 dollars ($432,000.00), subject to additions and deductions as herein provided, which sum is herein referred to as the Price.”
The contract made provision that the contractor should have the right, as construction proceeded, to direct any changes in the work to be made, which it might deem expedient, whether these changes increased or diminished the work. However, no such changes should be made “ except upon written order of contractor signed by an executive officer, stating the additional time allowed, if any, and the amount to be added or deducted from the Price.” The following clause was to govern in case of changes: “ Unit prices, if any are named in this contract, shall be used in determining the value of such changes.”
During the progress of the work some fifty changes were ordered made, and the cost of the work was greatly increased. The parties were unable to agree that the prices stated in the orders for the changes fairly expressed the additional cost. Consequently, the subcontractor, as provided in the contract, proceeded with the work, awaiting a subsequent determination by arbitration of increased costs. After completion, pursuant to an order of Special Term, modified by an order of the Appellate Division, arbitrators were appointed who took up the work assigned to them. An award was finally made in favor of the subcontractor against the contractor in the sum of $234,702.12, with interest. The contractor moved to set aside the award; the subcontractor moved to confirm the award. The award was confirmed, and judgment has followed for the amount of the award.
The contract does in fact contain a provision naming unit prices. The schedule therein given is preceded by the following clause: “ It is hereby understood and agreed that should any changes be made in the work as herein contemplated, the “ Price ” mentioned in article III shall be increased or decreased, as the case may be, by the amount of work added or omitted, multiplied by the following unit prices.” Then follow twenty-eight items, describing work to be done or materials to be furnished, and the agreed sum per unit to be paid therefor. Thus excavating by steam shovel is priced at $0.95 per cubic yard place measurement; hand excavating, for general purposes, is priced at $2.25 per cubic yard; for piers, pits and trenches at $2.45; for underpinning at $3.25. These prices are to prevail whether the additional excavation is done at a high or a low level, whether the
It was evidently the concept of the parties that all subcontracting work, whether done in precise accord with the work originally specified and planned, or whether done in accord with altered plans, increasing or diminishing the work, should constitute an integral part of the subject-matter of the express contract, to be governed by its terms, and to be paid for at contract prices. “All clauses of this Contract shall apply to any changes, omissions, or extra work in like manner and to the same extent as to the work contracted for, and no changes, omissions, or extra work shall annul or invalidate this contract.” With this thought in mind the parties made provision for arbitration as follows: “ In case the parties hereto disagree in relation to any clause in this contract, the question shall be referred to a Board of Arbitration consisting of three (3) disinterested parties, one nominated by Contractor, one by Sub-contractor, these two to select a third.” We have construed this particular clause to signify that disputes “ not being referable to ‘ any clause of this contract,’ were not made arbitrable by the parties.” (Matter of Smith Fireproof Constr. Co. v. Thompsom-Starrett Co., 247 N. Y. 277 , 279.) Specifically, the contract provided, in reference to alterations of the contract work, as we have already noted: “ In case of disagreement as to the adjustment of the Price or of the time of completion Sub-contractor shall proceed with the work and the determination of such amount or time shall be referred to arbitration as herein provided.”
The controversy to be arbitrated must be “ in relation to any clause in this contract.” Obviously a claim made
That the subcontractors, the petitioners herein, regarded the contract as having been utterly abandoned by the parties, and, therefore, wholly inapplicable to determine their claim, is clearly apparent. They presented a claim in quantum meruit for the recovery of the actual cost to them of all work done and materials furnished, plus a percentage for profit. They asked the arbitrators to determine that this entire contract as so affected, could not be done in accordance with the original contract plans, specifications, lump sum and unit prices in contract for additions and omissions and beg of the arbitrators to award it, the Stange Company, its full costs of the entire work, plus 10% profit, plus interest on defaulted payments to date, after allowing credit for cash payments made to date.” Said the counsel, in presenting
That the majority of the arbitrators, who made the award, agreed with the petitioners, is shown by the statements made by one of them. Thus Mr. Mueser said: “ The question to my mind is whether at the time when the parties made their contract, there was a meeting of the minds that the respondent (contractor) should have the right under the Change Clause to completely emasculate the contract leaving nothing but a shell.” In his judgment, “ It would be unfair, utterly without justice, if not fraudulent, to use the shell of an emasculated lump sum contract under the guise of a Change Clause to have the petitioner do work which in no sense he had intended to do, had not bid for and might be unfitted for or unorganized to do.” Finally, the arbitrator stated that the changes were of such character “ that they were beyond the intent of the change clause and in fact defeated the intent of the lump sum provision.”
The action of the arbitrators speaks even louder than the words used by them or the petitioners. Concededly, they made the award of $234,702.12 by no other method than the following: They found that the petitioning subcontractor had expended for the entire work done the sum of $911,784.28; that the total payments made to it by the contractor aggregated $677,082.16. Deducting the latter from the former leaves $234,702.12, and for that sum the award was made. True, these facts do not appear in the award itself. That document is artfully drawn, so that it appears therefrom that the arbitrators, having first found, on the evidence given, that the increased cost, due to the changes in the work, was $479,784.28, added that sum to the contract price of
In employing the figure produced by this proof as the sole basis of the recovery, the arbitrators arrived at a result which is clearly unwarranted. Their repudiation of the contract did not involve alone the contract terms providing for the use of unit prices to determine the cost of changes made; it involved a complete “ scrapping ” of the contract price. Thus, every advantage which the contractor may have secured to itself by the express contract has been swept away. Suppose, for instance, that the price of $432,000 for the original work covered material and labor to be furnished, the actual cost of which to the subcontractors would have been $632,000. Even if the arbitrators were entitled to disregard unit prices and go to total cost for the solution of their problem, the deduction from total cost, in order to determine additional cost, should have been, not $432,000, but $632,000. Not even a pretense is made that proof was given or a decision made to determine what would have been the actual cost of the original contract work. Mr. Mueser says: “ It is, indeed, true that in the endeavor to write the form of the award in full compliance with the order and the above contract requirement, the Chairman
The suggestion that the order of the Appellate Division modifying the Special Term order appointing the arbitrators is a final order which conclusively determines the authority vested in the arbitrators is entirely correct. However, the power to make the order was derived from the express contract between the parties and the order must itself be interpreted by the terms of that contract. The order contains no term providing for an arbitration other than that authorized by the contract. It provides that the arbitrators shall determine the “ increased costs and expenses of the said petitioners in any wise due to changes directed.” As there has been no comparison between the original and the altered plans, no estimate of the excess cost of executing the latter over and above the cost of executing the former, with due consideration given to the advantages, if any, afforded by the Price, there has
The judgment should be reversed, with costs in all courts, the order confirming the award reversed, and the motion to vacate the award granted.
Pound, Ch. J., Crane, Lehman and O’Brien, JJ., concur; Hubbs and Crouch, JJ., dissent and vote to affirm.
Judgment accordingly.
Cases cited
- Smith Fireproof Construction Co. v. Thompson-Starrett Co. 247 N. Y. 277 at 279 p. 38, p. 39, p. 41
- In re the Arbitration between Bullard & Morgan H. Grace Co. 240 N. Y. 388 p. 38
- Marchant v. Mead-Morrison Manufacturing Co. 252 N. Y. 284 p. 38
- Dodds v. Hakes 114 N. Y. 260 p. 38
- Moore v. Eadie 245 N. Y. 166 p. 38, p. 39
- Ice Service Co. v. Phipps Estates 245 N. Y. 393 p. 38, p. 39
- Fudickar v. Guardian Mutual Life Insurance 62 N. Y. 392 p. 39
- Sweet v. Morrison 116 N. Y. 19 p. 39