Majority
Headnote
1. Contracts (g 290[2] )—Building Contracts—Architects’ Certificates— Waiver.The mechanic’s lien was filed by one Michael Fuchs, the plaintiff’s assignor, against premises No. 381 Broome street, borough of Manhattan, N. Y., owned by the defendant. It was for work and labor performed and materials furnished pursuant to a contract in writing between the defendant, as party of the first part, and the plaintiff’s assignor as-party of the second part, made on the 16th day of August, 1905, by which the latter undertook to erect a seven-story building on the premises in question pursuant to drawings and specifications which were made a part of the agreement, and to do all of the work and furnish all of the materials, with the exception of “the installation of steam-heating apparatus and electric elevators for passenger and freight service, and all other electric work in said building,” for the gross sum of $34,739. Plaintiff’s assignor agreed to “perform the work, labor, and services under this contract in perfect accord and in connection with the other contractors who shall be employ
“And the party of the second part shall not set up or allege to excuse or justify any such default the neglect or omission of any contractor or other person employed on the said premises, unless he can do so rightfully, and then only in case he shall have given written notice of such neglect or omission to the superintendent, and for as many days as may elapse between the delivery of such notice and the doing of the work stated in the notice to have been neglected or omitted. The time in which the workmen and mechanics on the building shall be engaged in a general strike shall be allowed in computing the time for finishing the building.”
It was also further provided that the work should be done “to the full satisfaction” of Domenic Briganto, who is described in the contract both as superintendent and architect, “to be evidenced by his certificate” as therein provided; that, should any dispute arise “concerning the true construction of the plans, drawings, and specifications * * * or any part of either, the same shall be decided by the superintendent, and his decision shall be final”; that the superintendent “may condemn and reject any of the work or materials performed or furnished under this contract, and require the same to be taken down and removed from the premises by or at the expense of the party of the second part and may also direct the time of the doing of the several portions of the work”; that no certificate given by the superintendent or payment made under the contract should be deemed an admission by the owner that the work or any part of it had been done in accordance with the contract in the event that the fact should be otherwise, to preclude an action against the contractor for a failure to furnish materials of a good and proper quality, or to perform work “in every particular in a substantial and workmanlike manner,” or to faithfully perform the contract “in every respect.” It was further expressly agreed by the contractor that the certificates to be furnished by him as provided in the contract should “be regarded and taken as a condition precedent” to his making or asserting any claim or demand for money due under the contract, and that the payment of any installment of money thereunder “shall not be taken or construed as a waiver of the contract with respect to the condition thereof required before any subsequent payment” shall become due or payable. With respect to the final payment the contract provided as follows:
“The last payment shall not be payable unless the superintendent shall certify in writing that this contract has been fully performed and the work finished, completed and perfected in every way and respect to his full satisfaction,
and that all damages and charges which should or may be paid by the party ot the second part have been deducted from the said payment, and also a certificate from the party of the second part that all claims and demands for extra work and otherwise, of any kind or nature, in connection with this contract have been presented to the superintendent and are included in the said payment or payments.”
By the express provisions of the contract, payments were to be made in 10 installments from time to time as the work progressed from stage to stage as therein specified. The first five installments were fully paid. The sixth and seventh installments were $4,000 each. They were settled by the payment of $2,000 in cash on each, and the promissory note of the owner for the remaining $2,000 payable in four months. These notes aggregating $4,000 and the eighth installment of $2,239, the ninth of $4,500, and the final installment of $4,500, together aggregating $15,239, have not been paid. The contractor performed extra work for which he has been allowed by the referee the sum of $140. The referee thus found that the balance unpaid on the contract, together with this extra work, was the sum of $15,379. It is alleged in the amended complaint that the plaintiff’s assignor “duly fulfilled and performed all the conditions of said contract on his part to be performed” except as therein alleged. The only exceptions to this claim that the work had been fully performed in accordance with the requirements of the contract, and that the conditions of the contract had been duly kept and performed by the plaintiff’s assignor, found in the amended complaint, are with respect to time of performance and to obtaining the certificate of the superintendent 'and, architect.
Concerning the failure to perform within the time specified, it alleges excuses by which the completion of the work was delayed without fault on the part of the plaintiff’s assignor until the 15th day of March, 1906; and with respect to the certificates it alleges that they were “unreasonably, unjustly, and unfairly” withheld and refused. No waiver of performance of any provision of the contract on the part of 'the defendant is alleged, nor is there any allegation that the plaintiff’s assignor was prevented from performing any part of the work by any act on the part of the defendant or his agents or servants, with the exception of the provisions concerning the time of completion. Neither the plaintiff nor her assignor procured the certificates of the superintendent or architect for any part of the amount unpaid on the contract, as required by the contract. The procurement of certificates on the installments paid was waived by not being required; and doubtless the procurement of the certificate of the superintendent and architect with respect to that part of the sixth and seventh installments represented by the notes was waived, but no such waiver was pleaded. There is no evidence that the requirement of the contract with respect to the certificates concerning the other payments has been waived. At the close of the evidence and after a motion in behalf of the defendant for the dismissal of the complaint upon the ground, among others, that the plaintiff failed to establish the cause of action alleged, the record contains the following:
“Mr. Hill: The plaintiff asks leave to amend the amended complaint to conform to the proofs.
“The Referee: Motion granted. (Exception.)”
It cannot be held that a superintendent and 'architect who refuses in the circumstances here disclosed to certify that the contractor has performed his contract obligations is guilty of arbitrarily or unreasonably withholding such certificate. The architect’s certificate was a condition precedent to the right of the plaintiff to recover. We are of opinion that on the facts as found by the referee the judgment must be reversed, for it cannot be maintained that the contract was either completely or substantially performed, or that the plaintiff is excused from procuring the certificates."
We are also of opinion that the contractor failed to comply with the contract with respect to glass furnished for the windows in “gable walls on either side and'rear.” There is a special provision that these were to be of wire glass. This provision was complied with; but another was not. There was a special provision in the specifications requiring that French sheet glass should be used in the front windows.
There was still another provision of the specifications requiring that all glass to bfe used in the windows should be of the “best clear American cylinder glass.” This provision necessarily related to all of the windows other than the front windows, in which French glass was to be used, and it therefore embraced the windows in the gable walls on either side and in the rear. The undisputed evidence shows that the glass used in the windows in the gable walls and in the windows in the rear of the building was not clear, but was translucent. The learned referee with respect to this claim took the view that the glass admitted all the light 'necessary in view of the use to which the building was put. The attention of the contractor was drawn to this point before he put in the glass, and a sample of the kind of glass which the owner desired was presented to him and he was requested to use it. To this request he replied:
“It don’t call in the specifications for wire glass going to be selected by the owner. Whatever the specification calls for you should have.”
It. follows, therefore, that the judgment should be reversed and a new trial granted, with costs to the appellant to abide the event. All concur.
Cases cited
- Smith v. Brady 17 N. Y. 173 p. 176
- Van Orden v. MacRae 121 App. Div. 143 p. 177
- Easthampton Lumber & Coal Co. v. Worthington 186 N. Y. 407 p. 177
- Spence v. Ham 163 N. Y. 220 p. 177
- Crouch v. Gutmann 134 N. Y. 45 p. 177