Majority
Headnote
1. Mechanics’ Liens (§ 227[2] ) — Bond fob Discharge — Liability on Bond.On June 3, 1907, plaintiff entered into a written contract with Max Rapoport and Charles Ratner for the performance of certain work in connection with the erection of 17 buildings on the south side of Prospect place, in the borough of Brooklyn, belonging to the said Rapoport. On the 17th of January, 1908, plaintiff filed a notice of a mechanic’s lien against the said property. On the 14th of February, 1908, the said lien was discharged by the filing of a bond in accordance with the provisions of the statute. Thereafter this action was commenced against the contractors, the owner, and the sureties upon the said bond. Upon the trial thereof the complaint - was dismissed as against the sureties on the bond, and from the judgment entered in their favor this appeal is taken.
[1, 2] The sureties upon a bond given under such circumstances are not liable unless the plaintiff establishes the existence of a valid lien. Vitelli v. May, 120 App. Div. 448 , 104 N. Y. Supp. 1082 . The validity of the notice of lien filed by plaintiff is challenged upon the ground that it fails accurately to state how much labor has been performed and how much remains still to be performed, and what quantity of materials has been furnished and what quantity remains to be furnished under the contract, together with the agreed price or value thereof, and that it falsely states the amount unpaid to the lienor for such labor or materials. Lien Law, c. 49, of the General Laws; Laws of 1897, c. 418, § 9. To determine the true meaning of these provisions of the statute, this section must be read in connection with section 10 of the same act, which provides that:
“The notice of lien may be filed at any time during the progress of the work and the furnishing of the materials, or within ninety days after the
completion of the contract, or the final performance of the work, or the final furnishing of the materials.”
A fair construction of these provisions of the statute requires that, if a notice of lien is filed during the progress of the work, such notice should contain a statement of what labor has been performed and what materials have been furnished and what still remains to be done, with the amount unpaid to the lienor under the contract. Unless these provisions of the statute are substantially complied with, the lien is invalid.
“A mechanic’s lien never comes into existence unless the notice upon which it is founded substantially complies with the statute which authorizes the creation of such liens.” Toop v. Smith, 181 N. Y. 283 , 73 N. E. 1113 .
[3, 4] The notice of lien filed in this case contains a statement that “the labor to be performed is putting up all iron work on premises.” Counsel for respondents contends that this is a statement that no work has been done upon the premises described in the notice under the contract between the lienor and the persons employing him. This criticism seems to us unfounded; particularly when this sentence is read in connection with subsequent portions of the same notice. We think the fair construction of this language causes it to relate to the nature of the contract, rather than to that portion of the work which has been completed or remains uncompleted. This is apparent when we observe that the very next sentence is to the effect that the labor ' performed was putting up all iron work on 17 buildings. Then follows a statement that:
“The material furnished was fire escapes, iron beams, iron stoop-rails, and all other iron work necessary in constructing of (sic) said seventeen buildings.”
The notice then contains a statement that “the material to be furnished is. * * * ” This must either be construed as meaning that no material remains to be furnished, or that there is no statement upon the subject. The notice then contains a statement that the agreed price and value o-f said labor and materials is $3,100, and the amount unpaid to the lienor for such labor and material is $900. It appears from the complaint in this action that this lien was filed during the progress of the work. The language of the complaint is that on the 17th of January, 1908, and after the commencement and prior to the completion of the work and the furnishing of the materials provided for in the contract hereto annexed, the plaintiff filed a notice of lien. The date upon which plaintiff stopped the performance of labor and the furnishing of materials under the contract is not definitely stated in' the complaint; but from the statement that the balance claimed to be due became due on the 24th of January, 1908, we are justified in assuming that that date represented the termination of his work under the contract. It also appears that a portion of the materials called for, together with the necessary labor in connection with the installation thereof, was never performed, but that such omission was had at the request of the defendant contractors. Giving credit for the value of the work omitted, the complaint asks for judgment for $770, instead of $900, the sum stated to be due in the notice of lien.
The judgment appealed from should be affirmed, with costs. All concur.
Cases cited
- Toop v. Smith 181 N. Y. 283 p. 894
- Finn v. Smith 186 N. Y. 465 p. 895
- Ringle v. Wallis Iron Works 149 N. Y. 439 p. 895
- Felgenhauer v. Haas 123 App. Div. 75 at 108 p. 895