Majority
Headnote
1. Mechanics’ Liens, (§ 115[2] )—Enforcement—Liability of Owner for Advance Payments—Modification of Contract.The action by a subcontractor is to foreclose a mechanic’s lien, notice whereof was filed on February 27, 1911. But, on the previous January and February 17th, the owner had paid the contractor two sums, aggregating $450, and the obligation' of the contract released, although $125 was reserved by the owner to meet the expense of laying the sidewalk when suitable weather should permit it to be done.
[1] But the plaintiff invokes section 7 of the Lien Law, and asserts that the payments were ineffective to avoid his lien, inasmuch as they were not payable until the completion of the work, and hence not until the sidewalk should be laid. To sustain this contention, the plaintiff must prove that the payments were accelerated “for the .purpose of avoiding the provisions- of” the Lien Law. To maintain that issue the plaintiff proved the owner’s knowledge of the lien before the payment. Indeed, such knowledge was deemed sufficient evidence of purpose to avoid the lien in Wolf v. Mendelsohn, 87 N. Y. Supp. 465 , and in Behrer v. McMillan, 114 App. Div. 450 , 100 N. Y. Supp. 35 ,
[2] But it is urged that the owner knew that the contractor was not paying its men, that it was irresponsible in that regard, that it had not paid the balance due the plaintiff, and that the latter had given the owner notice of the fact that he must look out for him, and that the owner had promised to attend to it. There is no evidence that the plaintiff was deterred by such assurance from filing his notice. The work was finished in November. The lien was not filed until February 27th thereafter. The substance of plaintiff’s argument is that, where the owner knows that the contractor is in default in his payments for labor and material.contributed by others to the building, he must see to it that the default is met before he makes advance payments to the contractor. There is no such obligation at common law, and the statute does not contemplate it. It would make the owner the supervisor of the affairs of the contractor, necessitate an accurate knowledge of his affairs, and constitute him a trustee for the material-men before they made him such by filing liens. But it is superadded that the defendants promised to attend to it. That would not make him liable at law. No action for fraud could rest on such promise of future action. The failure to attend to it is not evidence that the owner paid the contractor to escape attending to it.
[3] The fact is that the work was not done in July, 1910, as agreed, and the owner in writing extended the terms of payment to December 1, 1910, and agreed to pay him the balance due, “provided, however, he delivers to me a receipt from one William J. Wagner” (plaintiff), “a subcontractor on the Forrest avenue house, showing that his entire claim for labor1 and material furnished on said house has been paid.” The plaintiff was not privy to his agreement. When the money was finally paid, and the relations of the contractor and owner to the building contract ended, the contractor showed the owner a letter, purporting to be written by the plaintiff to the contractor, offering to settle his claim for a sum named and notes indorsed. The owner, assuming that the matter would be met in that way, settled with the contractor. It may have been done inconsiderately, and without proper regard for his promise to attend to it; but that does not show that it was fraudulently done. The plaintiff’s claim that the work- was not done when the payment was made reaches too far. The contractor
The judgment should be reversed, and judgment should be entered dismissing the complaint, with costs. All concur.
Cases cited
- Behrer v. City & Suburban Homes Co. 114 App. Div. 450 p. 51
- Dodin v. Dodin 191 N. Y. 530 p. 52