Majority
Headnote
Contracts @=^319—Construction—Compensation—“Services.”On or about May 3, 1911, the plaintiff made a contract in writing with the defendant for equipping defendant’s factory with a system of fire-extinguishing apparatus at a cost of $1,133. The agreement provided that, if plaintiff’s work should be discontinued by fire or other cause not the fault of the plaintiff “there shall become and be immediately due and payable, from you [defendant] on account of the work a sum equal to the value of .the materials, labor, and services furnished at „the date of such discontinuance.” It was also stipulated that title should remain in the plaintiff to the materials and equipment until fully paid for, and that, if it became necessary for the plaintiff to remove any part of the equipment because of default in payment, the plaintiff should be paid the reasonable value of installing and removing the equipment and any other expense incurred for loss or injury to the property.
On June 17, 1911, before any part of the equipment was actually attached to the building, the defendant’s factory was destroyed by fire. The plaintiff introduced evidence tending to show the rendition of services necessary to the performance of its contract prior to the fire, and evidence was also given of the value of these services. The defendant claimed that, as no part of the equipment was actually attached to the building on June 17, 1911, no materials, labor, or services were furnished by the plaintiff within the meaning of the contract. The court sustained this view, and- at the close of plaintiff’s case granted defendant’s motion for the dismissal of the complaint.
The plaintiff was entitled to a more favorable construction of the contract. The agreement is that in the contingency provided for defendant shall pay for the value of the materials, labor, and services furnished, and the use of the word “services” indicates that in such event the plaintiff’s right should not be limited to the value of the labor performed in the actual annexation of the apparatus to the
In Dickinson v. Gray (Ky.) 8 S. W. 876 , the contract under construction provided that in the event of the cancellation of the contract of the principal contractor the subcontractor should be paid for labor done and materials “furnished” up to the date of such cancellation, and the Court of Appeals of Kentucky held that the word “furnished” was not equivalent to the word “delivered,” that the right of the subcontractor to recover for materials furnished was not restricted to such materials as had been delivered, inspected, and received at the time of the cancellation of the contract, but that he was also entitled to be paid for materials procured or prepared to be furnished for the work.
We think that the plaintiff was entitled under the agreement sued upon to recover the reasonable value of the services actually and necessarily furnished in preparing the specific equipment, and also for the value of materials, if any, actually furnished at defendant’s building and destroyed or lost in the fire. The plaintiff made out a prima facie case, and it was error to dismiss the complaint.
Judgment reversed, and a new trial ordered, with costs to appellant to abide the event.
Cases cited
- H. G. Vogel Co. v. Reinhardt 89 Misc. Rep. 606 p. 261
- Hayes v. Gross 9 App. Div. 12 at 40 p. 262