Majority
Headnote
1. Mechanics’ Liens <§=>163—Exteni^-Statutory Provisions.The defendant Bassett agreed to build a house for the defendants Flynn for the sum of $1,829, to be paid upon the certificate of the architect. The plaintiff furnished lumber therefor, and the action is to foreclose its lien, filed therefor. The original contract under which Bassett agreed to construct the house provided that 80 per cent, of the labor and material, furnished on the premises as the work progressed, was to be paid; the remaining 20 per cent to be paid on completion and acceptance of the work or within 10 days thereafter.
At the time plaintiff’s notice of lien was filed, Bassett had put into the structure labor and material of the value of $1,653.91, and no payments under the contract had been made to him at that time. The lien was filed July 27, 1912, and the defendant owners had actual notice of the filing about three days thereafter, as the evidence shows and the trial judge finds. The trial judge further finds that on or about the 25th day of August, 1912, Bassett abandoned this contract and refused to complete the work, and that thereafter the owners completed the work, furnishing the material for and on account of the contractor, Bassett, pursuant to the terms of the contract, at a total cost of $1,679. For the difference between $1,829, the contract price, and $1,679, what the owners paid for completing the contract, $150, the court decided that plaintiff was entitled to recover upon its lien.
[1, 2] Plaintiff excepts, and challenges the correctness of this de
In Van Clief v. Van Vechten, 130 N. Y. 571 , 29 N. E. 1017 , the Court of Appeals, in construing the provisions of chapter 342 of the Laws of 1885, containing similar provisions as are now embodied in the present Lien Law, laid down the following rule for determining the extent to which a mechanic’s lien attaches to the property:
“(1) If anything is due to the contractor, pursuant to the terms of the contract, when the lien is filed, it attaches to that extent.
“(2) If nothing is due to the contractor, according to the contract, when the lien is filed, but a certain amount subsequently becomes due thereunder, the lien attaches to the extent of that sum.
“(3) If nothing is due to the contractor, pursuant to the contract, when the lien is filed, and he abandons the undertaking without just cause, but the owner completes the building according to the contract, and under a provision thereof permitting it, the lien attaches to the extent of the difference between the cost of completion and the amount unpaid when the lien is filed.”
At the time of the filing of the plaintiff’s notice of lien, Bassett had furnished to within $147.09 in value of the entire contract price and more than half of the total cost of completing the building, including what the owners afterward paid to complete the same. According to the terms of the contract he was to be paid 80 per cent, of the labor and material furnished on the premises as the work progressed. Assuming that this provision of the contract means, not the actual value of the labor and materials furnished, but the proportionate value based upon the contract price, the contractor had earned, and there was due him then, more than the amount of the plaintiff’s lien. Eighty per cent, of one-half of $1,829 would be upwards of $700, while the-plaintiff’s claim is but a little over $600. Even though the contractor may have abandoned his contract, and the owner would be compelled to pay more than the contract price, that is no answer to the enforcement of this lien for the full amount. While the plaintiff’s right is derivative, in a sense, it is more than that. It is a right founded upon a statute, which by its express terms gave the plaintiff a lien on the amount due from the owner to the contractor at the time of the filing of the lien for the material so furnished by the plaintiff and used in the construction of the house, with the owner’s consent. I quote as follows from Ray on Mechanics’ Liens:
“But the subcontractor is entitled to a lien on all that is due from the owner to the contractor a.t the time of the filing of the lien, and if the contractor
later defaults the owner cannot counterclaim against the amount due at the time of filing the lien; the default being subsequent to such time. The amount to which the lien may attach may be increased after the time of filing, but it can never become less than the amount due at such time. Anisansel v. Coggeshall, 83 App. Div. 491 , 82 N. Y. Supp. 430 ; Foshay v. Robinson, 137 N. Y. 134 [ 32 N. E. 1041 ].” Ray on Mechanics’ Liens, p. 334.
The cases cited sustain the quotation, and I think the principle applies to this case.
[3] 2. Furthermore, I think the evidence shows that, at the time of the transaction which the trial court has found to be an abandonment, the owners recognized the plaintiff’s claim and promised to pay it. While it is true that the contractor refused to proceed with the work, that refusal was based upon his lack of means, as he stated, although at that time a large amount had been earned by him under the contract and was being withheld, and unjustly so, as I think. But, notwithstanding such refusal, he did proceed with the work thereafter, upon the promise of the owners, as the plaintiff contends, to pay the amount of the pay roll each week of the contractor and his men, and pay the outstanding bills, including that of the plaintiff. I think the testimony of the contractor and the architect supports this contention. Flynn admits paying the other bills, but disputes the fact that he agreed to pay the plaintiff’s bill. He says he did not know about it ; but the evidence shows, and the finding is to the effect, that he had actual notice of the plaintiff’s lien on or about the 30th day of July, 1912, which was nearly a month before this transaction.
I think the findings should be modified, by striking out the finding of an abandonment, and in lieu thereof a finding should be made substantially in accordance with plaintiff’s contention, as before stated. The judgment should be modified, by declaring that the plaintiff has a valid lien for the full amount of its claim and interest. The other provisions of the judgment should be made tó conform with such modification, and, as so modified, the judgment should be affirmed, with costs to the appellant against the respondent owners.
Order entered nunc pro tunc as of date of argument, May 19, 1915; the defendant Jerry Flynn having died since the argument. All concur; ROBSON and FOOTE, JJ., only upon the first ground stated in the opinion.
Cases cited
- Van Clief v. Van Vechten 130 N. Y. 571 p. 727
- Foshay v. Robinson 137 N. Y. 134 p. 728