Majority
Headnote
1. Appeal—Review—Mechanics’ Liens.The plaintiff in September, 1889, entered into a contract with the defendant Jones, by which the former was to construct a dwelling house for .a specified sum. In December of the same year the plaintiff entered into a contract with the defendant the tile company, whereby the latter was to furnish the trim and cabinet work for the house, but not to set them in place, for the sum of $4,946. Shortly after the house was finished, or claimed to be finished, the plaintiff filed a mechanic’s lien for the balance due him on his contract with the defendant Jones, and for certain extra work, and the •defendant the tile company filed its lien for the unpaid balance claimed to be due it from the plaintiff. Thereafter the plaintiff brought this action to enforce his lien. In his complaint he alleged that the tile company had failed to complete its contract with him,, by delay in' time of performance, and by furnishing him improper and defective materials; that by such breach plaintiff had been damaged in a sum greater than the balance due the tile company on the contract, and, as against it, prayed that the lien filed by the tile company be discharged. The tile company answered, asserting the validity of its lien. The defendant Jones answered, denying that the plaintiff had completed his contract, and also counterclaiming for damages for delay and defective work. The action was tried before a referee, who found that the plaintiff had substantially performed
The notice of appeal taken by the tile company is directed only to the plaintiff, and was not served on the defendant Jones. As the defendant Jones, the owner of the property affected by the lien, is not a party to this appeal, we do not see how it is possible to reverse the judgment, in so far as' it voids the lien filed by the tile company. By neglecting to make him a party to this appeal, it has lost its right to reinstate the lien, even if the judgment below is erroneous. Mechanics’ Lien Law, § 15, provides that in any action brought to foreclose the lien, if the party failed for any reason to establish the lien, he may nevertheless recover therein, on the contract, such sum as may be due him. As the question of the liability of the plaintiff to the tile company, on the contract between them, could be determined, and was actually litigated, on the trial, the judgment herein would conclude the tile company in any subsequent action. We think, therefore, it has the right to prosecute this appeal and have the judgment reviewed, even though it cannot regain its lien.
The first point to be disposed of is the plaintiff’s claim that the appellant failed to obtain a certificate from the architect as to the completion of its work, which was required by the contract. The referee has found that the appellant did substantially perform its contract. The architect, upon the completion of the building, gave a certificate to the owner that the plaintiff had performed his contract for the construction of the house. It is true, as claimed by the plaintiff, that this certificate did not necessarily imply a certification that the appellant had fulfilled its contract with the plaintiff; for non constat but that the plaintiff himself furnished the trim necessary for the construction of the house. But when the appellant applied to the architect for its certificate the architect declined, upon the ground that he had given a certificate to the owner, and that was
The evidence amply justified the finding of the referee that the appellant was guilty of gross delay in the performance of its contract. We do not assent to the plaintiff’s claim that the appellant took the risk of any delay on the part of the architect in failing to furnish detailed plans or drawings. We think, under the contract, the performance of this duty by the architect was a condition precedent to any duty on the part of the appellant; but the evidence of the architect as to the general practice in the business was that, whenever a party wished or required detailed drawings, he applied to the architect. This evidence as to the custom is uncontradicted, and it also appears from the appellant’s evidence that whenever it needed drawings it sent to the architect for them. While many of these drawings were not furnished until a time long after that at which appellant should have finished its contract, it does not appear, nor is there any claim, that the architect delayed in furnishing the drawings when they were applied for. The delay in. performing the contract seems, therefore, to have been solely the fault of the appellant.
The appellant claims that, conceding it was in default in respect to time of performance, an improper rule of damages was held against it. We think not. Though the evidence does not show that the defendant was informed of the time within which the plaintiff, under his contract with Jones, was bound to construct the house, still it abundantly appears that he knew that the plaintiff had a contract for such construction. He also knew that the materials were for this particular house; that they were not such as could be supplied in the market, but had to be got out, fashioned, and formed in accordance with special designs. Under this state of facts the case falls directly within the rule of Booth v. Mill Co., 60 N. Y. 487 , and the appellant was bound to indemnify the plaintiff against any damage he might suffer under his contract with Jones. There is a further answer to this claim of the appellant: It knew that its delay in furnishing the material contracted for would necessarily delay the completion of the house, and had there been no contract between plaintiff and Jones, but the plaintiff had been the owner of the property, we cannot see why the rule of damage adopted by the referee would not have been entirely fair and applicable.
As to the second item of set-off allowed the plaintiff as against the appellant, we are of opinion that the amount allowed by the referee was not justified by the evidence. It appears that plaintiff had made a contract with a cabinet worker to set up the trim and woodwork, and also construct fences and coal bins, for the sum of $550. The plaintiff, as a matter of fact, paid the cabinet worker $2,200. The plaintiff claims that this increased expense was occasioned by the fact that defective material furnished, by the appellant had to be tom out of the house, and new material set up, and also that the
The judgment appealed from should be reversed, except so far as it cancels the lien of the appellant, and a new trial ordered on the issues between the plaintiff and the appellant; costs to abide event. All concur.