Majority
Headnote
1. Contracts—Compliance with Specifications—Question for Jury.It is claimed by the plaintiff that it became entitled to the contract price upon doing the work in accordance with the plans and specifications, and that, if leaks occurred within five’ years after completion, it simply became bound to remedy them, without prejudice to the right to recover the agreed amount. This contention it is not necessary to consider, for we think it was error-to take from the jury the question whether, in fact, the work done conformed to the specifications. MacKnight testified that it did;, but this was merely a general statement, amounting to but little more than his conclusion or opinion. There is no pretense that he was.present when the work, or even the substantial part of it, was-
In view, too, of this state of the evidence, we think expert testimony upon the subject was competent, and that it was error to rule out the testimony of an expert who was familiar with the ground and the surrounding conditions. We refer to the witness Vaughan. He had been in the business of waterproofing cellars for 42 years and was fully acquainted both with the plans and specifications, and with the condition of these premises, having been a bidder for the ■contract which the plaintiff obtained, and having thoroughly gone into all these matters in order to make his bid. He was asked to say whether, in his opinion, the cellar could have been made watertight if the plans and specifications had been complied with. The question was excluded, and the defendant’s counsel excepted. Later, tire learned trial judge seems to have altered his views as to the competency of such evidence; for the architect, Duncan, was allowed to state his opinion that the cellar would have been waterproof if the work had been done as agreed, that a break the size of a pin hole would have caused the leak, and that the leak occurred because the waterproofing was not intact and continuous. This evidence should have been submitted to the jury for their consideration. It further weakened the already weak and inconclusive testimony of Mac-Knight, and it thus strengthened the defendant’s position in requesting the submission to the jury of the question of fulfillment. Of course, expert testimony is inadmissible where the matter at issue is the existence or nonexistence of a fact capable of direct proof, if such proof is supplied. That, however, is not this case. Nor do we wish to be understood as intimating that the plaintiff, in this class of cases, must be held to an unreasonable measure of proof. When, to all appearance, work has been done as required, and fulfills its purpose, general testimony to this effect may, and should, suffice. But where the work does not fulfill its purpose, but fails in the very essence of it, the mere general statement of an interested party that he has fulfilled his contract, or testimony substantially to that effect, cannot be treated as adequate, even if the opposite party is unable to point out in detail the specific defect.
It is next claimed that, whether or not the premises were made water-tight in accordance with the plans and specifications, the plaintiff at least made them dry, and that the defendant thus became liable, either by reason of the plaintiff’s inherent right to complete in
Finally, there was no acceptance of the work as done, constituting a waiver of the defect, or any conduct estopping the defendant from now insisting upon the nonfulfillment. On March 30,1896, Commissioner Collis wrote to the architect, in answer to a number of letters from the latter as to the condition of the courthouse building. In this letter he stated that there could be no further delay; that it was necessary to take possession of the building; that this should be done, and the use of the ejector continued, without prejudice to the defendant’s rights against the plaintiff; and that no certificate should, for the present, be given to the latter. Accordingly, possession was taken, and boilers, coal bins, engines, and electric light apparatus put in. There was here no acceptance of the work. The commissioner simply acted upon the existing condition of things. This was his plain duty. There was nothing in his determination, at that late day, to take possession of the building, and to make it ready for occupancy, which can change or qualify the defendant’s right to insist upon the fact of nonfulfillment. Such “right would be affected only by an actual, voluntary acceptance of the work as a fulfillment of the contract, with an express or implied promise to pay therefor. There is nothing of the sort here.
We think, therefore, that the questions presented by the defendant’s requests should have been submitted to the jury, and that the direction of a verdict was error.
The judgment should be reversed, and a new trial ordered, with costs to the appellant to abide the event. All concur.
Cases cited
- Bonesteel v. Mayor 22 N. Y. 162 p. 142