Majority
Headnote
1. Quantum Meruit—Rescission of Contract.The action is for work, labor, and materials furnished by plaintiff to defendant. The answer is a general denial and breach of contract. The case was tried before a justice of the
The plaintiff entered into a contract with defendant to do certain carpenter work, and furnish the necessary labor and materials therefor, at plaintiff’s own cost and expense. Defendant agreed to pay •for the work the sum of $1,600, partly in weekly payments not exceeding $150, and the final payment upon a full compliance with the contract. The work was to be completed on or before .December 1,1901. . Through no fault of plaintiff, a strike occurred on November 9, 1901, and lasted until December 14, 1901, when defendant came to an arrangement with the men. The strike was caused by the acts of defendant, and the negotiations were carried on for a settlement by defendant’s ■ agent, to the exclusion of plaintiff. The fact that the time for the completion of the contract expired during the strike cannot be allowed to militate against the plaintiff under the circumstances here disclosed, and this is conceded by defendant. The work proceeded from December 14, 1901, to December 31, 1901, when the defendant canceled the contract. Defendant’s reasons for canceling the contract are founded, according to his contention, on the following facts, viz.: On or about December 28, 1901, a check for $178 was sent by defendant to plaintiff, with the suggestion that it be used to pay the carpenters their weekly wages. Part of it was so applied, but not enough to pay the carpenters in full, and, as a result, they struck against plaintiff, and refused to proceed with their work until paid in full. At great inconvenience, and some expense, according to defendant, the agent of defendant came on from Philadelphia, where defendant’s office or place of business is' situated, met the plaintiff, and called upon him to pay the men under the contract, or have the contract canceled. Plaintiff refused, and defendant was compelled to pay the men himself $150 in order to have the work continued, and suffered the loss of a full day’s work. Thereafter, and on December 31, 1901, he wrote a letter to plaintiff, canceling the contract under the following clause:
“If M. O’Dwyer shall get behind in his portion of the job, so as to prejudice the probability of the said Geo. W. Smith & Go. being able to finish in the time designated, or if he shall do bad work, it shall be lawful for the said Geo. W. Smith & Co., at their option, either to put on such men and to supply such labor as shall be needed, at the expense of the said M. O’Dwyer, or to cancel the residue of this contract, and proceed to finish the same by other parties, with the right to retain the damages thereby occasioned them out of the moneys in their hands to the said M. O’Dwyer belonging, and to sue for any loss which they may not be able to recover.”
Thereupon the plaintiff’s connection with the work ceased, and defendant finished the same at his own expense. Plaintiff’s version is somewhat different. He says he put on extra men at the request of defendant, with the understanding that defendant would advance more money weekly than the $150 called for by the contract, as defendant was very anxious to complete the work within the time agreed upon between defendant and the owners of the premises; that the said check of $178 was insufficient to pay the men in full; and that when the men struck the defendant demanded that plaintiff pay the men or
Judgment affirmed, with costs. All concur.
Cases cited
- Clark v. Mayor of New York 4 N. Y. 338 p. 90
- Wright v. Reusens 133 N. Y. 298 at 305, 31 p. 90
- Purdy v. Nova Scotia Midland Ry. & I. Co. 11 Misc. Rep. 406 p. 90
- Simmons v. Ocean Causeway of Lawrence 21 App. Div. 30 at 47 p. 90
- Brewster v. Wooster 131 N. Y. 473 p. 90
- American Corrugated Iron Co. v. Eisner 39 N. Y. Super. Ct. 200 p. 90
- Thomson v. Poor 147 N. Y. 402 p. 90