Majority
Headnote
3. Municipalities—Construction of Waterworks—Independent Contractors—Negligence.The aqueduct commissioners of the city of New York, on the 20th of August, 1899, advertised for sealed proposals for'“building overflow and blow-off sewers, water pipes and appurtenances in connection with the Jerome Park Reservoir of the New Croton Aqueduct * * * and particularly for p sewer on East 204th Street in said City.” The plaintiffs submitted a proposal, which was accepted, and on the 18th of September, 1899, a contract was entered into between them and the aqueduct commissioners, acting for and on behalf of the city, one of the provisions of which required the plaintiffs to commence work within 10 days thereafter, and to complete the same on or before July 1 1900. Anticipating, however, that they would be unable to finis1’ the work within the time stipulated, they,' on the 23d of June, 1900, obtained an extension until November 30, 1900, on which date they obtained a second extension to June 1, 1901. The work to be done and the materials to be furnished by the plaintiffs under their contract was to dig a trench and place therein water mains and a sewer running from the easterly end of East 204th street at its junction with Mosholu Parkway south to Jerome avenue and north in Jerome avenue to a high-service pumping station, and was part of the work undertaken by the city to perfect a system of water supply made necessary by the building of Jerome Park reservoir. As a part of this system, the department of water supply, on the 26th of October, 1899, made a contract with one Gildersleeve to make the necessary excavation and construct the foundation walls for a high-service pumping station at or near one end of the work agreed to be performed by the plaintiffs, and to make the necessary connections with such work when completed. Gildersleeve agreed to commence work within 10 days after the execution of his contract, and to complete the same within 200 days thereafter (Sundays
I am of the opinion that the judgment should be reversed. There is no basis for the claim made by the plaintiffs against the city, and the evidence does not sustain the jury’s verdict. Before the plaintiffs could recover, they were obligated to show some breach of duty on the part of the defendant, either by omission or commission, and this they failed to do. It is conceded that the city has paid all it agreed to pay under the contract, but it is claimed it is liable for the damages sustained outside and independent of the contract.
The city certainly had the right to make the contract which it did with Gildersleeve. That was neither a negligent nor an unlawful act. The work to be performed under that contract was a necessary part of the general undertaking to supply the city with
The contract clearly contemplated that the plaintiffs were, at their own expense, to take care of all the water that came into the sewer, whether by percolation or through pipes and sewers. O’Brien v. The Mayor, 139 N. Y. 543 , 35 N. E. 323 ; Burnham v. City of Milwaukee, 100 Wis. 55 , 75 N. W. 1014 . Otherwise, there is no meaning to the words that the plaintiffs should “provide for the flow of all sewers, drains and water courses,” and that the city should- “have the right to connect any sewer or sewers * * * at any time” with the one which the plaintiffs had agreed to build. The rights of the parties, therefore, so far as the water in question is concerned, must be determined by the contract itself, and there are no provisions in it which obligated the city to take care of such water or prevent it flowing into plaintiff’s trench. There was no negligence, as we have seen, in letting the contract to Gildersleeve,
In the Uppington Case the court said:
“When, however, the city has power to let the work, and it enters into contract with competent contractors doing an independent business, who agree to furnish, the necessary materials and labor, and make the entire improvement according to specifications prepared in advance, for a lump sum or its equivalent, they are not the servants or agents of the city, but are independent contractors, and the city is not liable for their negligence, even when it reserves the right to change, inspect, and supervise to the extent necessary to produce the result intended by the contract, provided the plan is reasonably safe, the work is lawful, is not a nuisance when completed, and there is no interference therewith by municipal officers which results in injury.”
The facts in this case, it seems to me, bring it squarely within the rule thus laid down. Gildersleeve agreed to do the work, according to specifications prepared in advance, for a specified sum of money. No claim is made but what the plans were reasonably safe, or but what the work was lawful. It was not a nuisance, because it was authorized by law, and there was no interference with his work by any of the municipal authorities. The plaintiffs’ damage was not caused by any act of the city, and the proof offered failed to establish a cause of action, for which reason the verdict is not sustained by the evidence, and the judgment and order appealed from must be reversed and a new trial ordered, with costs to appellant to abide event. All concur. .
Cases cited
- O'Brien v. Mayor of New York 139 N. Y. 543 p. 875
- Uppington v. City of New York 165 N. Y. 222 p. 876
- Berg v. Parsons 156 N. Y. 109 p. 876
- Engel v. Eureka Club 137 N. Y. 100 p. 876
- Butler v. Townsend 126 N. Y. 105 p. 876
- Herrington v. Village of Lansingburgh 110 N. Y. 145 p. 876
- Devlin v. Smith 89 N. Y. 470 p. 876
- Kelly v. Mayor of New-York 11 N. Y. 432 p. 876
- Pack v. Mayor of New York 8 N. Y. 222 p. 876