1. New York (city of) Consolidation Act—Laws 1882, chap. 410, § 64— Contract for work, etc . on public buildings—Necessity of— Certificate of public officer.The reversal by the general term is sought to be sustained by two propositions argued on behalf of the city: first, that no necessity existed for the change authorized by the new or supplemental contract, and, second, that it involved an expenditure of more than $1,000, and so was invalid unless submitted to public competition. Our judgment is adverse to both propositions.
Much of that expenditure has been necessary, not in the hard and narrow sense of the word, but relatively to' the standard of taste and beauty adopted as the controlling guide. Much was reasonably to be deemed necessary there which elsewhere could not be, and would verge upon pure extravagance. A restaurant in that park should not disgrace the standard of its surroundings. It was better not-to build it at all than with a cheap parsimony and bad taste. These considerations might rightfully influence the constructing board and take their place among the reasonable necessities of the work. In their plans the main vestibule and cafe, and even the principal staircase, were to be finished in pine. Undoubtedly, when so finished, the job would be “complete,” but would it also be “perfect”?' Great changes have come about in the construction of interiors. The use of hard woods has become the rule where any degree of elegance is sought, and a cafe, in the Central Park, finished in pine even to the staircase rails-
The remaining question is whether the change ordered and made involved an expenditure of over $1,000. The general term has so held upon the ground that to the $975, which was the contract price of the change, must be added the cost of the pine fitting under the original contract. We think that is a mistaken view. The original contract was to be performed for about $29,000. That was founded upon sealed bids, and included the fitting of the rooms and construction of the staircases. The contractor was not released from that work, and did perform it, and so was entitled to his full pay under the old or original contract. If he had used cherry, without any arrangement for an extra compensation, he would simply have completed the original contract for the original price.
The supplemental contract was for extra work and material beyond the original contract price, and the price of that was simply the $975. I think we may see it in another way by the inquiry, how much of additional expenditure was incurred by the change. The $29,000 was payable for the work of the original contract. That required doors, archtraves, bases and staircase. All these were built and furnished and the contract-price thus earned, but an additional expenditure of $975 was involved in the change ordered from pine to cherry. The total expenditure was increased only by the value of the extra material and labor beyond that already covered by a valid contract; and the two contracts together when both were fulfilled did not add to the original and authorized expenditure more than $1,000. The order made related to and covered only the excess of value due to the extra work and material. The price of the pine and its fitting went as far as it could in paying for the ■cherry and its fitting and the new contract began and its expenditure commenced at the point where the old one was exhausted. Viewing the matter thus we think the contractor should have his pay which he has fairly earned.
The order of the general term should be reversed and that of the special term of the superior court be affirmed, with costs.