Majority
Headnote
Evidence—Guaranty.This action was brought to foreclose a mechanic’s lien filed by the plaintiff on the 22d day of July, 1892. The plaintiff and defendant entered into a contract by which the plaintiff was to furnish and set up complete a furnace of sufficient heating capacity.to heat defendant’s house, and complete same in a good and workmanlike manner. The contract provided that the sum of $1,045 should be paid to the contractor (plaintiff) in installments, as follows: $470 when the rough piping was in; $470. when the entire apparatus was set up and completed; and the balance ($105) 30 days from the last payment, and within 30 days after the contract was completely finished,—providing that in each of said cases the architect should certify in writing that all the work had been done to his satisfaction. It is further provided by the contract that no certificate given or payment made under this contract, except the final certificate and final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, against any claim of the owner. On November 21,' 1892, the architect gave a certificate in the following language: “ November 20, 1892. E. D. Haskins: Louis W. Gay, contractor for heating, is entitled to the second payment of $470, as per contract. Amount previously paid, $470. Amount of contract, $1,045.00. John S. Rowe.” This sum was paid, and receipted for by the plaintiff, on the 22d day of November, leaving the final installment of $105 unpaid. No other or further certificate was given, and no final certificate, as required by the contract, was given, unless this one can be so considered. This becomes important when we consider that the plaintiff in the specifications guarantied that the apparatus would warm the rooms to which radiation is conducted to 70° Fahrenheit in the coldest winter weather. The work was to be done according to the drawings and specifications, and they became a part of the contract, and must be resorted to to determine whether the certificate given November 21st was the final certificate contemplated by the contract. The provision deferring the final payment of $105 for 30 days was probably intended for the purpose of affording the owner and architect time and opportunity to determine whether the work was completed according to the terms of the contract, before he could truthfully certify that the -work was done to his satisfaction. This is especially the case when the sufficiency of the heating must be determined within the 30 days limited by the contract. Hence the contract provides, as I understand it, that before the final payment of $105 becomes absolutely payable the architect must certify in writing that all the work upon the performance of which the payment became due has been done to his satisfaction. The certificate of the architect given to secure the second payment of $470, while not in the language of the contract, is probably a sufficient compliance with its terms, under the authorities. Wyckoff v. Meyers, 44 N. Y. 145 ; Snaith v. Smith, 57 St. Rep. 86 . And a certificate was required, by the terms of the contract, before the last installment became payable, before the defendant would be absolutely concluded from setting up the defense that the work was not in accordance with the terms of the contract. If
Concurrence
(concurring).—By the contract between the parties the heating apparatus was to be completed as soon as it reasonably could be, and was in fact completed prior to December 22, 1892. All the work and material used was satisfactory to the defendant, and the whole price of the apparatus became due and payable on January 22, 1893. The contract for the work guaranties that the apparatus will warm all rooms to which radiation is set to 70 degrees Fahrenheit, in the coldest winter weather. The defendant pleaded, and on the trial offered to prove, a breach of this guaranty. The evidence was excluded, on the ground that the work and material used in constructing the heating apparatus -complied in all respects with the contract, and that, therefore, the plaintiff had performed this guaranty. To be more literally exact, the trial court held that the parties by the contract made the architect an arbiter of the question as to whether the warranty had been fulfilled by the plaintiff, and tho^ the certificate of the architect that all the work had been completed to his satisfaction/and in accordance with the contract, conclusively establishes the fact of such fulfillment. I am of. the opinion that there is no connection between the certificate of the architect and the guaranty by
Cases cited
- Wangler v. Swift 90 N. Y. 38 p. 55