Majority
Headnote
1. Contracts—Interpretation.—1. While quite agreeing with the learned referee that a contract existed between McKone and Eobinson, and that that contract included the tiling, plastering, and papiermaché work, we cannot concur in the view that the contract price was $1,200. The undisputed evidence seems to establish the contrary. According to the defendant McKone’s own testimony, the only limit put upon the cost was that it should not exceed $1,500. ” The same thing is shown by the defendant’s Exhibit E. This was a card on which-Eobinson first wrote the details of the work which he was to do. At the fooi of it, in McKone’s handwriting, are the words, “ Will not run over
2. We are also unable to agree with the learned referee that the plaintiffs became substituted as contractors in the place of Robinson. The order of August 30, 1894, does not effect any such substitution. There is only one possible construction to be put upon it, and that is that it gives the plaintiffs, as subcontractors under Robinson, the security of McKone’s responsibility up to the amount of $1,200. If the plaintiffs became chief contractors in Robinson’s stead, they Avould be entitled to receive Robinson’s compensation. But, even if we should assume, contrary to the fact, that Robinson’s compensation on August 30, 1894, Avas fixed at $1,200, it Avould still remain true that the plaintiffs Avere not absolutely entitled to this sum. They were to receive the “ amount of their bill,” which was “ not to exceed ” the sum of $1,200. The learned referee admits that, on its face, this is what the order means, but says that nevertheless, the evidence as a Avhole shows that such a substitution was effected. After a careful perusal of his opinion, and examination of the evidence, we are unable to see that he refers to, or that the record discloses, any fact or circumstance permitting such an inference. In fact, the testimony of McKone and his attorney, Eustis, sIioavs that the question .of the retention of Robinson or the substitution of the plaintiffs Avas directly discussed, and the former course deliberately chosen. This AA7as
3. From the foregoing it results that the plaintiffs should not have been nonsuited on their second cause of action. McKone was liable to Kobinson in the sum of $1,500 if the work done was of that value. Kobinson assigned away his right to recover $1,200 of this amount, but remained entitled
4. We are unable to agree with the referee that the defendant McKone proved that he was entitled to deduct the sum of $761 .'80 as the value of the uncompleted work. It was simply proved that McKone paid out this amount. There is no evidence that the work done was of that value. The mere fact of payment, standing alone, is not sufficient evidence of value. Gurnb v. Railroad Co., 114 N. Y. 411 , 414; 23 S. R. 748.
5. We also think that the learned referee erred in his disposition of the question of costs. The defendant McKone made an offer of judgment under section 738 of the Code of Civil Procedure. This offer was in these words :
“The defendant, Joseph F. McKone, hereby offers to allow judgment to be taken against him in this action establishing the amount of. the plaintiffs’ lien at the sum of one thousand dollars and costs.”
The offer was not accepted, and, as the plaintiffs failed to establish a lien to the amount of $1,000, the referee awarded costs to the defendant from and after the date of the offer. The appellant contends that the offer was unauthorized, for the reason that the mechanic’s lien act (Laws 1885, c. 342) provides a complete and comprehensive scheme upon the general subject, which excludes the section of the Code in question, and prevents offers of judgment thereunder. We do not agree with this view of the statute. It is true that the act contemplates a complete sj^stem for creating and enforcing mechanics’ liens, but it expressly retains the ordinary procedure in civil actions for the foreclosure of mortgages upon real property except as therein otherwise provided. Section 8. .This procedure embraces offers of judgment under section 738, and there is certainly nothing in the mechanic’s lien act which is inconsistent therewith, or which provides “ otherwise.” Section 19 of the mechanic’s lien act has no relation to offers of judgment. That section merely allows an offer to pay a given sum into court. Acce¡3tance of the offer entitled the lienor neither to the money nor to judgment. It simply permits the deposit, and thereupon substitutes the money for the land, discharging the lien upon the latter. This is an entirely different thing
As to the Winter appeal, we are satisfied that the finding of the referee that the item of $10 for building the stairway was included in the contract between Robinson and Winter is amply sustained by the evidence. This item was thus properly disallowed as against the defendant McKone, and judgment has been given the appellant for the remainder of his claim.
The judgment, so far as appealed from by the plaintiff, should be reversed, and a new trial ordered, with costs to abide the event; so far as appealed from by the defendant Winter, it should be affirmed, with costs.
All concur.