p. 524. as' actual necessity required, making the expense of the work as moderate and reasonable as the circumstances permitted.”
The plaintiff excepted to this portion of the instructions, for • the reáson that “ the same authorizes the jury to allow the defendant, , and to deduct from'the claim of the plaintiff, as a part of the expense of changing the mill over so as to make it conform to the contract, the cost of the new machinery put into the mill, amounting to $1100.”
' The jury returned a verdict- by which “ they find the issue herein in favor of the defendant, but that the defendant is not entitled to recover damages against the plaintiff in excess of the plaintiffs claim against the defendant.” Judgment was rendered on the verdict, and the plaintiff sued out this writ of error. '
Mr. G. W. Hazleton for plaintiff in error.
I. tinder' contracts of the description of that in dispute, in this'case, where the thing furnished is to' be satisfactory to the purchasing party and he neglects .to return or to offer to return it, but takes it .into possession and uses it either in the shape in which it is, or for the purpose of making it over -into.something different, he thereby obligates himself to pay for it at the .contract price,' and is not at liberty to recoup the cost of such reconstruction in an action for the price. McCarren v. McNulty, 7 Gray, 139 ; Brown v. Foster, 113 Mass. 136 ; Wood Reaping Machine Co. v. Smith, 50 Mich. 565 ; Hallidie v. Sutter Street Railroad, 63 California, 575 ; Hoffman v. Gallaher, 6 Daly, 42 ; Singerly v. Thayer, 108 Penn. St. 291 ; Silsby Manuf. Co. v. Chico, 24 Fed. Rep. 893 ; McClure v. Briggs, 58 Vermont, 82; Balt. & Ohio Railroad v. Brydon, 65 Maryland, 198; McCormick Machine Co. v. Chesrown, 33 Minnesota, 32; Gray v. Central Railroad of New Jersey, 11 Hun, 70 .
The defendant .being under no legal duty to accept the machinery, which could be enforced, — in other words, having the power to' accept or reject, the case stands as if the plaintiff. in. error ha'd left with the defendant an article at a given
p. 525price to examine and test subject to. approval. Witherby v. Sleeper, 101 Mass. 138 ; Fairfield v. Madison Manufacturing Co., 38 Wisconsin, 346 ; Dewey v. Erie Borough, 14 Penn. St. 211 ; S. C. 53 Am. Dec. 533 ; Spickler v. Marsh, 36 Maryland, 222; Prairie Farmer Co. v. Taylor, 69 Illinois, 440.
II. But if it be held that the contract in this case is subject to a different rule from that laid down in the cases already cited,, in other words, that these cases do not state the law, then we claim that the doctrine invoked by the defendant ought not to be applied to this case': 1st. Because the notice served does not convey any intimation of such expenditures as were charged: 2d. Because such alleged damages were manifestly not within the contemplation of the parties: 3d. Because the rule invoked by the defendant is not the proper test and measure of damages in such. case. White v. Brockway, 40 Michigan, 209; Merrill v. Nightingale, 39 Wisconsin, 250; Boothby v. Scales, 27 Wisconsin, 626; Bonnell v. Jacobs, 36 Wisconsin, 59.
III. It has long been the settled doctrine of the State of Wisconsin that a party may return or offer to return an article which does not comply with the terms of the warranty, and recover back what he has paid. Woodle v. Whitney, 23 Wisconsin, 55.
IV. A question is raised as to the admissibility of Geissner’s testimony to show the rental value of the mill. The plaintiff in error submits that this evidence ought not to have been excluded.
Butler v.
Mehrling, 15 Illinois, 488;
Alfonso v.
United States, 2 Story, 421 ;
Sturgis v.
Knapp, 33 Vermont, 486;
Whitbeck v.
N. Y. Central Railroad Co., 36 Barb. 644 ;
Whitney v.
Thatcher, 117 Mass. 523 ;
Cliquot’s Champagne, 3 Wall. 114 .
Mr. John' T. Fish, for defendant in error,
cited: Snyder v. Western Union Railroad Co., 25 Wisconsin, 60; Clark v. Baird, 9 N. Y. (5 Selden) 183; Teerpenning v. Corn Exchange Insurance Co., 43 N. Y. 278 ; Lincoln v. Saratoga & Schenectady Railroad, 23 Wend. 425 ; Brill v. Flagler, 23 Wend. 354 ; Norman v. Wells, 17 Wend. 136 ; Lamoure v. Caryl, 4 Denio,
p. 526370
; Transportation Line v. Hope, 95 U. S. 297 ;
Stone v.
Covell, 29 Michigan, 359;
Clark v.
Rockland Water Power Co., 52 Maine, 68;
Westlake v.
St. Lawrence Ins. Co., 14 Barb. 206 ;
Tucker v.
Mass. Central Railroad Co., 118 Mass. 546 ;
Pennsylvania Company v.
Roy, 102 U. S. 451 .
after stating the case- as above reported, delivered the opinion of the court.
The principal position taken in the argument for the plaintiff is. that the defendant, having received and retained the machinery'furnished under.the contract sued on, was bound to pay the contract price; and in support' of this position., cases were cited, holding that under a contract to manufacture or to furnish a chattel satisfactory to the purchaser, the purchaser, if he takes possession of and uses it, thereby conclusively, accepts it as satisfactory, and binds himself to pay the whole contract, price.
Considering the ,instructions given at the plaintiff’s own request, and the grounds on which the plaintiff excepted to the other instructions of the court, it is, to say the least, doubtful whether this point is open. But, assuming it to be open, it clearly cannot be sustained, and the: cases cited are inapplicable.
The plaintiff’s agreement was not for a sale of the machinery, subject to a condition that it should bé satisfactory to the purchaser. But it was an agreement, not only' to furnish machinery of a certain description and x quality, but also to set it up and put it in complete operation in the defendant’s mill.' The machinery was to be erected on the defendant’s land and made part of his mill; and one instalment of the price was to be paid on the delivery of the machinery there, and before the plaintiff had completed the work to the satisfaction of the defendant In such a case, it would be most unreasonable to compel the defendant, in order to entitle him to avoid paying the whole .contract price, or to recover damages for the plaintiff’s breach of contract, to undergo the expense of taking out the machinery, and the prolonged interruption of his business
p. 527during the time requisite to obtain new machinery elsewhere. The rule of damages, adopted by the court below, of deducting from the contract price the reasonable cost of altering the construction and setting of the machinery so as to make it conform to the contract, is the only one that would do full and exact justice to both parties, and is in accordance with the decisions upon similar contracts.
Benjamin v. Hillard, 23 How. 149 ;
Railroad Co. v. Smith, 21 Wall. 255 ;
Marsh v. McPherson, 105 U. S. 709 , 717;
Cutler v. Close, 5 Car. & P. 337;
Thornton v. Place, 1 Mood. & Rob. 218 ;
Allen v.
Cameron, 3 Tyrwh. 907;
S. C. 1 Cr.
& M. 832.
The notice given by the defendant to the plaintiff “ to put the mill in repair so as to do good work ” was sufficient to cover all alterations necessary to accomplish that end.
No error is shown in the exclusion of Geissner’s testimony as to the rental value of a mill which he had never seen and knew nothing of. Whether a witness called to testify to any matter of opinion has such qualifications and knowledge as to make his testimony admissible is a preliminary question for the judge presiding at the trial; and his decision of it is conclusive, unless clearly shown to be erroneous in matter of law. Perkins v. Stickney, 132 Mass. 217 , and cases cited; Sorg v. First German Congregation, 63 Penn. St. 156 .
Judgment affirmed.