Majority — White C.J.
Syllabus
APPEAL FROM THE COURT OF CLAIMS.delivered the opinion of the court.
The petition , claimed $51,736.00 because of an alleged violation of a contract to carry the mails over a mentioned route in Alaska. The United States demurred on the ground that no cause of action was stated; and the court having sustained the demurrer and dismissed the petition, 47 Ct. Cl. 146 , the case is here. The text of the petition therefore is the matter we are called upon to consider. It covers sixteen pages of the printed record. We shall seek to rearrange its contents so as to enable us with accuracy and yet with brevity to state the substance of the petition in order to determine whether a cause of action was stated.
It was alleged that on September 15, 1905, the United States advertised for proposals to carry the mails over a route in Alaska from Valdez to Eagle, a distance of 428 miles, and back. The advertisement conveyed information concerning the route and the duty which would rest upon the contractor, and contained the following:
“The Postmaster General may order an increase of service on a route by allowing therefor not to exceed a pro rata increase on the contract pay. He may change schedules of departures and arrivals in all cases, and particularly to make them conform to connections with railroads, without increase of pay, provided the running time be not abridged. The Postmaster General may also discontinue, change, or curtail the service in order to place on the route superior service, or whenever the public
Under this proposal the bid of John B. Crittenden to do the called for work at $46,000.00 per annum was accepted, and on the first of February, 1906, a contract was entered into between the Government and Crittenden and his sureties, John Miller and Charles H. Cramer, for performing the service for the Sum of the bid for the period of four years from the first of July, 1906 to June 30, 1910. The written contract contained specifications as to the character of the work, its requirements and the mode of its performance which it is not here necessary to detail. Besides a full stipulation giving the Postmaster General authority to enforce the contract and all its provisions by imposing penalties and forfeitures and by discontinuing the contract in case of non-performance, as embodied by the provisions which are reproduced in the margin,[2] the contract contained the following:
In addition the statutory provisions governing the subject and the Post Office regulations having the force of law which had been stated in the advertisement for proposals were by reference incorporated and made a part of the contract by the following provision:
“That this contract is further to be subject to all the conditions imposed by law, and by the several acts of Congress relating to post offices and post roads, and to the conditions stated in the pamphlet advertisement of September 15, 1905.”
It was averred that shortly after the making of the contract Miller, the petitioner, who was one of the sureties of
1 And it is hereby further agreed that liability for all fines and deductions imposed upon a party of the first part by the Postmaster General, for failures and delinquencies in the performance of service under his contract shall be assumed and borne by the party of the second part, *9 and, if necessary, the Auditor for the Post Office Department may enforce this agreement by proper deductions from any compensation due the party of the second part for service performed under this subcontract. And it is hereby further agreed that for any additional service required by the Postmaster General, and not hereinbefore expressly stipulated, the party of the second part Shall be allowed not to exceed a pro rata increase of compensation; and, in case of decrease, curtailment, or discontinuance of service, as full indemnity, a pro rata of- the one month’s extra pay allowed by the United States to the party of the first part, and, unless previously herein stipulated, not to exceed a pro rata compensation for the service retained.
“In the preparation of the forms of advertisement, proposal and contract in suit, the government officials adopted the regulation in force, and such advertisement, proposal and contract were drawn and printed for general use, and the proposal and contract were presented for execution, without particular regard to the physical, climatic, or other conditions then existing or that might exist along the line of that route during the contract period of four years. At the execution of the proposal and contract, and of the subsequent contract of subletting,. Crittenden and petitioner did not think or believe that the contract in suit would be discontinued or terminated in any manner or form, but on the contrary, they believed that the contract in suit would be in full force and effect during the whole contract period, and they named the amount of annual compensation in that belief. They expected that they would encounter losses of profits in a portion of the contract period, but would earn good profits before the contract period ended and for the whole contract period. Had Crittenden and the petitioner believed otherwise than as above stated, they would not have executed either of the contracts for that annual compensation, nor would petitioner have made the arrangements and expenditures in the early part of 1903, [1908] hereinafter described. On the contrary, petitioner made such arrangements and expenditures in the belief that the contract would be in force for the full contract period. Peti
The petition moreover alleged that the conditions which existed at the time the contract was made in the region covered by the mail route which it embraced, caused it to be extremely difficult and hazardous to human life and property to carry the mails over the route described and within the time specified in the contract. In many places it was averred, the government trails were not fit to be used because of their bad condition, and it became necessary to build new ones. With much amplitude, the petition described the almost insurmountable difficulties with which the performance of the contract was environed: the cutting of trails, the building or repairing of bridges, the erecting of sheds, the transporting at an enormous expense along the route of the means to sustain men and horses, the struggle in doing so in winter through ice and snow, and in spring and summer, the overcoming of obstacles resulting from flood and many other causes. Indeed, the facts detailed, being taken as true, establish that the performance of the contract was surrounded by difficulty of the
It was alleged that counting on the fact that the contract would be allowed to go to its termination, after the petitioner became the sub-lessee he. spent a large amount of money in putting the route in fair condition, in provisioning the same by shipping food for men and horses at freight rates which were enormousr all of which he would not have done had he been informed of the intention of the Government to discontinue the ctintract before the end of the contract period. That upon the same reliance, as a mea is of utilizing his equipment, he bought out the rights and assumed the obligations of a contract which had been made by a firm known as Scott & Frase for carrying the mails from a point known as Tanána Crossing to Eagle, the place where the contract of which the petitioner was the sub-contractor terminated.
It was alleged that although in September, 1908, the Government discontinued the contract of petitioner, it did not discontinue the mail service, to which that contract related, but only restricted it, that is cut out about 190 of the 428 miles between Valdez and Eagle and in the balance had the mails carried by contracts exacting a less onerous and less frequent service, these contracts having been made as emergency contracts, without advertisement, without affording the petitioner any opportunity to bid
These being the averments of the petition, it is obvious, the questions are as follows: First, did the contract confer the authority on the United States to discontinue its performance, and, if so, did it give power to the Post' Office authorities after the contract was discontinued to deal, with the mail routes which the contract had previously embraced in such a manner as was found necessary to sub-serve the public interest; second, if yes, did the averments of the bill show such a state of facts as would justify the conclusion that the action of the Post Office authorities in exerting the lawful power of discontinuance was so impelled by bad faith as to cause the exertion of the otherwise lawful power to be invalid and void?
That in explicit terms the express authority was given to the United States to discontinue the execution of the contract is so plainly the result of the proposal which led up to the contract, of the text of. the contract itself, of the Post Office rules and regulations which by the text were incorporated in and made a part of the contract, as to leave no room for discussion. Indeed this result was in terms admitted by the allegations of the petition to which we have referred, and the challenge of the power to discontinue therein made, conceded that the terms of the contract gave the power, but relied only upon the assertion that such terms, although express and positive, should be read out of the contract as inapplicable to the situation to which the contract related, that is, the carriage of the mail over the designated route in Alaska.
That the power to discontinue the contract left the Government free after such discontinuance to make such contracts as were deemed best, is also the unambiguous result of the proposals submitted by the Government, of the text of the contract itself, and of the context of the postal rules and regulations which by reference were incorporated into the contract. In fact, while the context establishes this result so clearly and so obviously as to leave no room for extraneous reasoning, if such were not the case, and purpose and intent required to be looked at, it is manifest that to deny that such power existed would be to set aside and frustrate the public policy upon which the right to discontinue rests. It would render the exertion of the power futile — or cause it to be inadequate to protect the public interest since it would deprive of means of remedying the evil to cure which the right to discontinue was exerted. The irresistible force of the contract itself on the subject has been previously pointed out by this court in a case which was cited by the court below in its clear opinion. Slavens v. United States, 196 U. S. 229 , 233, 236.
Making the assumption for the sake of the argument only that the existence of a fraudulent motive or of bad faith impelling the exercise by the Postmaster General of the authority conferred upon him to discontinue, be a factor in determining whether an otherwise valid power had been lawfully exerted, such concession could have no possible reference to this case, since it is expressly'conceded in the argument at bar that no such charge was made in the petition and none is relied upon, the only claim being that a power not conferred was exerted or that if one which was given was exercised, the circumstances disclosed were of such a character as to justify the legal conclusion that it was so grossly inequitable to bring
Affirmed.
Footnotes
- 1 And it is hereby further stipulated and agreed by the said contractor and his sureties that the Postmaster General may annul the contract or impose forfeitures in his discretion for repeated failures or for failure to perform service according to contract; for violating the postal laws or regulations; for disobeying the instructions of the Post Office Department; for refusing to discharge a carrier, or any other' person having charge of the mail by the contractor’s direction, when required by the Department; for subletting.service without the consent of the Postmaster General, or assigning or transferring this contract; for combining to prevent others from bidding for the performance of postal service; for .transmitting commercial intelligence or matter *7 which should go by mail, contrary to the stipulations herein;.for transporting persons so engaged as aforesaid; or for the failure of the contractor to give his personal supervision to the performance of the service, and to reside upon or contiguous to the route; that the Postmaster General may annul the contract, whenever the contractor shall become a postmaster, assistant Postmaster, or member of Congress, or otherwise legally incompetent to be concerned in such contract: and whenever, in the opinion of the Postmaster General, the service can not be safely continued, the revenues collected, or the laws maintained on the road or roads herein.
Cases cited
- Canal Co. v. Hill 15 Wall. 94 p. 2
- Chicago, Rock Island & Pacific Railway Co. v. Denver & Rio Grande Railroad 143 U. S. 596 p. 2
- Winona & St. Peter Land Co. v. Minnesota 159 U. S. 526 p. 2
- United States v. Utah, Nevada & California Stage Co. 199 U. S. 414 p. 2, p. 5
- Succession of Serralles v. Esbri 200 U. S. 103 p. 2
- Sun Printing & Publishing Ass'n v. Moore 183 U. S. 642 p. 2
- Ripley v. United States 223 U. S. 695 p. 3
- Chicago, Milwaukee & St. Paul Railway Co. v. Hoyt 149 U. S. 1 p. 3
- Slavens v. United States 196 U. S. 229 at 236 p. 3, p. 5, p. 15
- Garfielde v. United States 93 U. S. 242 p. 3, p. 4
- Hinckley v. Pittsburgh Bessemer Steel Co. 121 U. S. 264 p. 3
- Anvil Mining Co. v. Humble 153 U. S. 540 p. 3
- Roehm v. Horst 178 U. S. 1 p. 3
- Prairie State Bank v. United States 164 U. S. 227 p. 3
- United States v. Behan 110 U. S. 338 p. 3, p. 4, p. 5
- Robertson v. Frank Bros. 132 U. S. 17 p. 4
- District of Columbia v. Barnes 197 U. S. 146 p. 4
- United States v. Burns 12 Wall. 246 p. 4
- United States v. Gleason 175 U. S. 588 p. 4
- Kihlberg v. United States 97 U. S. 398 p. 4
- 153 U. S. 576 153 U. S. 576 p. 4
- Martinsburg & Potomac Railroad v. March 114 U. S. 549 p. 4
- Chicago, Santa Fé & California Railroad v. Price 138 U. S. 185 p. 5