Majority
Headnote
[1] Street Law—Improvement Act op 1911—Time op Performance — Delay in Securing Extension — Effect op Curative Provisions.—In view of the curative provisions of sections 26 and 82 of the Street Improvement Act of 1911, an assessment levied for certain street work under the provisions of that act cannot be declared invalid on account of a delay of two days in obtaining an extension of time within which"'to complete the work. ■This is an appeal from a judgment foreclosing a lien for an assessment levied for certain street work in the city of St. Helena under the provisions of the Improvement Act of 1911. The complaint alleges, in due form, the performance of all things required by the Improvement Act to be done up to the signing of the contract on the seventh day of November, 1912. It alleges the execution of the contract, but does not .contain any statement as to what time was therein fixed by the superintendent of streets for the beginning of the work or the completion thereof, other than the general allegation that the superintendent of streets “fixed the time for beginning said work and the time for completing said work.” The complaint then goes on to allege that the plaintiff “did and caused to be done all the work in said contract . . . and duly performed on its part in every respect the said work according to . . . the terms of the contract”; that the work was approved and accepted by the superintendent of streets on the sixteenth day of May, 1913, and that thereupon the assessment and diagram for the work was made by the superintendent of streets, in due form, with his warrant and the engineer’s certificate attached; their recordation, issuance to plaintiff, demand of plaintiff for payment, return on the assessment, its recordation, and that no appeal was taken to the city council. The above are not all the allegations of the complaint but a skeleton of such as are material in this appeal.
The defendant Bank of St. Helena- defaulted. The defendant -Sarah J. Watson, who will hereafter be called defendant, appeared first by demurrer, both general and special, in which the complaint was demurred to specially upon the ground that the complaint was uncertain in that it could not be ascertained therefrom the time fixed by the superintendent of streets for the commencement or the completion of the work. Other grounds of special demurrer are alleged, but these are the only special grounds urged on this appeal. The demurrer was overruled, whereupon the defendant answered admitting all the allegations of the complaint excepting that it was denied that the plaintiff had completed the work according to the terms of the contract, or
At the trial the plaintiff introduced in evidence the assessment, warrant, and diagram, and thereupon rested its case. The defendant offered to prove that the work was not completed within the ninety days fixed in the contract, and that the time for completion was not extended by the city council until February 7, 1913. Upon the objection of the plaintiff that the evidence proposed was incompetent, irrelevant, and immaterial, the court excluded it. No offer was made to show that the work was not completed within the time granted by the counsel on the seventh day of February, 1913.
The main question presented upon this appeal is whether, in view of the curative provisions of sections 26 and 82 of the Improvement Act of 1911 (Stats. 1911, p. 730), the alleged defect in failing to grant an extension in which to complete the work within the time limited by the contract, was cured.
Section 26 provides that “no assessment, warrant, diagram or affidavit of demand and nonpayment, after the issue of the same, and no proceedings prior to the assessment, shall be held invalid by any court for any error, informality, or other defect in the same, where the resolution of intention of the council to do the work, has been actually published as herein provided, and said notices of improvement have been posted along the line of the work, as provided in section 5 of this act, before the passage of the resolution ordering the work to be done.” Section 82 reads as follows: “This act shall be liberally construed to the end that its purposes may be effective. No error, irregularity, informality, and no neglect or omission of any officer of the city, in any procedure taken hereunder, which does not directly affect the jurisdiction of the city council to order the improvement, shall avoid or invalidate such
These sections will not stop inquiry concerning those parts of the proceedings which are essential to due process of law, that is, “jurisdictional” (Ramish v. Hartwell, 126 Cal. 443 , [ 58 Pac. 920 ].)
It is claimed by the appellant that by failing to extend the time for completion of the contract within the time limited by the contract for its performance, jurisdiction was lost by the council. In other words, that the requirement that the time shall be extended during the time for the performance fixed in the contract is “jurisdictional,” and the error in failing to so extend it is not one that could have been remedied by the council on appeal, and that, therefore, the defendant was not required to appeal to the council. The respondent contends that under the authority of Chase v. Trout, 146 Cal. 350 , [ 80 Pac. 81 ], this requirement is not “jurisdictional,” and that under the provisions of the act quoted above the defect, if any, was cured.
In the case of City Street Improvement Co. v. Pearson, 181 Cal. 640 , [ 185 Pac. 962 ], the court in passing on the provisions of an ordinance of the city of San Francisco for doing street work, and the provisions. of which in relation to appeal to the council were practically identical with section 26 of the Improvement Act of 1911, said: “Curative provisions in a law of this character may cure any defect that does not go to the jurisdiction of the board over the proceeding.”
“In any proceeding designed to subject the property of an individual to the burden of tax or assessment, certain elements are essential to constitute compliance with the mandates of the state or federal constitutions. It is agreed on all hands that no curative act can deprive a property owner of the right to resist a pretended assessment which, if enforced, would deprive him of his property without due process of law, or otherwise infringe his constitutional rights. But short of this, there is no more reason for denying to the statute before us than to that involved in the case of Chase v. Trout, 146 Cal. 350 , the effect of foreclosing any attack based upon the failure to pursue
The foregoing was quoted with approval and applied to the “curative” clause of the Improvement Act of 1911, in Watkinson v. Vaughn, 182 Cal. 55 , [ 186 Pac. 753 ], and the court further said in pointing out the distinction between the sb-oalled jurisdictional requirements called for by the statute and those jurisdictional requirements which are necessary for a compliance with “due process of law”: “The very question of what defects in street improvement proceedings could be cured under such provisions as those of section 16 and section 66 of the present act was considered at length in Chase v. Trout, 146 Cal. 350 , [ 80 Pac. 81 ]. The argument was thus made, that no so-called ‘jurisdictional defect could be thus cured.’ In response, however, to this argument, the decision made a distinction between those so-called jurisdictional requirements which are called for by statute and those jurisdictional requirements which are necessary for a compliance with the constitutional provision that property shall not be taken without due process of law, or with other constitutional provisions, and it was held that while failure to comply with jurisdictional requirements of the later class could not be cured, a failure to comply with
Speaking of the very defects urged here, the court said in Chase v. Trout: “The legislature undoubtedly could have enacted a valid law, which would have authorized the extension of the contract after the time first fixed had expired, ... or that the time to begin work need not be fixed in the contract. . . . Having such power, it likewise has power to declare that after the issuance of the bonds it shall be conclusively presumed that such directions, if any such exist, have been followed.”
[1] Prom the overwhelming weight of authority from Chase v. Trout down, we are compelled to conclude that the assessment cannot now be declared to be invalid on account of the delay of two days in obtaining an extension of time in which to complete the work. It will be admitted
It' may be conceded that it is a “jurisdictional” requirement that the time must be extended within the time limit of the contract, but ip is not one of the jurisdictional requirements necessary to constitute due process of law, and hence is cured.
Having arrived at the foregoing conclusion,, and in view of the admissions in the answer that no appeal was taken to the council, and of the issuance of the assessment, diagram, and warrant and the return thereon, it follows that the evidence offered was properly excluded.
[2] There was no error in admitting the assessment, diagram, and warrant in evidence, for the allegations of the complaint as to these matters, and the making of a due return by the contractor, were admitted by the answer, and the plaintiff could have rested its case thereon. (Baisch v. Eildebrandt, 146 Cal. 721 , [ 81 Pac. 21 ].) [3] Nor was there any reversible error in overruling the special demurrer, as the omission to state the time fixed by the superintendent of streets for the commencement and completion of the work was cured by the allegations of the answer stating these facts. (Booth v. Oakland Bank of Savings, 122 Cal. 19 , [ 54 Pac. 370 ]; Daggett v. Gray, 110 Cal. 169 , [ 42 Pac. 568 ]; Burns v. Cushing, 96 Cal. 669 , [ 31 Pac. 1124 ].)
The judgment is affirmed.
. Kerrigan, J., and Bardin, P. J., pro tern., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on February, 24, 1921. (See Oakland Paving Co. v. Whittel Realty Co., 185 Cal. 113 , [ 195 Pac. 1058 ].)
All the Justices concurred.
Cases cited
- Ramish v. Hartwell 126 Cal. 443 p. 690
- Chase v. Trout 146 Cal. 350 p. 690, p. 691
- City Street Improvement Co. v. Pearson 181 Cal. 640 p. 690
- Imperial Land Co. v. Imperial Irr. Dist. 173 Cal. 660 p. 691
- Watkinson v. Vaughn 182 Cal. 55 p. 691
- Bd. of Educ. of S.F. v. Hyatt 152 Cal. 515 p. 692
- Schaffer v. Smith 169 Cal. 764 p. 692
- Beveridge v. Livingstone 54 Cal. 54 p. 693
- Fanning v. Schammel 68 Cal. 428 p. 693
- Dougherty v. Coffin 69 Cal. 454 p. 693
- Dougherty v. Nevada Bank 81 Cal. 162 p. 693
- Brock v. Luning 89 Cal. 316 p. 693
- Palmer v. Burnham 120 Cal. 364 p. 693
- Union Contracting & Paving Co. v. Campbell 2 Cal. App. 534 p. 693
- Raisch v. Hildebrandt 146 Cal. 721 p. 693
- Booth v. Oakland Bank of Savings 122 Cal. 19 p. 693
- Daggett v. Gray 110 Cal. 169 p. 693
- Burns v. Cushing 96 Cal. 669 p. 693
- Bates v. Hadamson 2 Cal. App. 574 p. 694
- McSherry v. Wood 102 Cal. 647 p. 694
- Harney v. Benson 113 Cal. 314 p. 694
- California Improvement Co. v. Reynolds 123 Cal. 88 p. 694
- Oakland Paving Co. v. Whittell Realty Co. 185 Cal. 113 p. 694