Majority
The plaintiff, Frank A. Calhoun, herein referred to as “Calhoun,” sued the defendant, Huntington Park First Savings & Loan Association, a corporation, herein referred to as the “Association,” to recover the amount of his claim for material furnished and services rendered in connection with certain construction work, alleging that the Association was the holder of construction loan funds deposited with it for the payment of such work; that he filed a stop notice with it, as provided by law; and that, disregarding this notice, the Association thereafter transferred all of such funds to an escrow holder payable to trustees for the benefit of creditors, without withholding therefrom sufficient money to satisfy his claim. The defendant answered and cross-complained bringing into the action the escrow holder, Security Title Insurance Company and the trustees, Glen Behymer and Ralph Hoffman. Judgment on the complaint was rendered in favor of Calhoun and against the Association for the amount in question, without interest; and on the cross-complaint directing the trustees to make an accounting and decreeing payment to the Association of a prorata share of the funds remaining in escrow. The Association appeals from that part of the judgment awarding Calhoun recovery on his complaint. Calhoun appeals from that part of the judgment denying him interest. No appeal is taken from that part of the judgment directed to the issues raised by the cross-complaint.
In the early part of 1955 the Association loaned Holly Manors, Inc., $410,960 to be used in the construction of residential units upon two tracts of land; received trust deeds upon this property securing payment of this loan; entered into a construction loan agreement with the borrower whereby the funds loaned were assigned to it to be disbursed in payment of labor and materials furnished in the course of such construction. The loan agreement contained provisions respecting the manner of such payment; declared that a work stoppage in the construction for an aggregate of 15 days would constitute a default under its terms; and provided that, in the event of any default thereunder the “Association shall withdraw any sum or sums on deposit with it under the terms of this
On January 26, 1956, Calhoun filed a stop notice and a bond with the Association, in accord with the provisions of section 1190.1, subdivision (h) of the Code of Civil Procedure, which provides that a mechanic or materialman who has furnished labor or material to a construction project, the cost of which is payable from the proceeds of a building loan placed in a fund for that purpose by the borrower, may give notice of his claim to the person holding such proceeds who, upon the posting of a bond by the claimant as therein provided, “must withhold from the borrower or other person to ivhom said owner may be obligated to make payments or advancements out of said fund sufficient money to answer such claim, and any lien that may be filed therefor.” (Code Civ. Proc., § 1190.1, subd. (h).)
After receiving this stop notice the Association did not disburse any part of the remaining funds to the borrower. However, without retaining the amount of plaintiff’s claim, the Association deposited all of the remaining funds in an escrow with instructions to pay the same to the cross-defendants Behymer and Hoffman as trustees for the benefit of creditors of the borrower subject to certain conditions precedent hereinafter noted. The escrow instructions were executed only by the Association.
The deposit in escrow was made on March 29, 1956. The instructions were dated March 28, 1956, and followed a proposal made by the Association at a meeting of creditors, over which the plaintiff presided as chairman, which had been held earlier on the same day. Before this time the Association had started foreclosure proceedings under its deeds of trust; several claimants, including the plaintiff, had filed mechanics’ liens against the property; the United States Government also had filed a lien for unpaid taxes; and the claim of a person
Calhoun had served on the creditors’ committee for several months before the March 28th meeting. He continued to serve on this committee after the construction funds were placed in escrow upon assurances from Behymer that his doing so would not commit him to the arrangements proposed by the Association, nor preclude him from pursuing separate remedies so long as he did not execute the requested written power of attorney. He remained on the committee with the hope and for the purpose of persuading the Association to apply all of the money in the construction fund to the mechanic’s lien claimants, which would have required it to make other arrange
The following chronology of events is pertinent: On March 30fh, two days after the creditors meeting, Calhoun's attorney wrote the Association, referred to the stop notice, and stated that Calhoun claimed to be the “rightful owner of those portions of the above loan funds which are due him as you have been heretofore notified”; on April 6th, the Association purchased the property at the foreclosure sale; on May 22nd it was served with process in the instant action, which had been filed on May 21st; and on June 14th, after determining that the mechanic lien claimants, including the plaintiff, had released their lien claims against the property, the Association amended its instructions to the escrow holder and authorized partial disbursement of the funds on hand even though the claims of the United States Government and Everson had not been satisfied, and even though, in the meantime, it had been advised that Calhoun refused to sign the power of attorney to Behymer. The attorney for the defendant Association testified that before the distribution was made he understood that Calhoun “was causing some trouble and wasn’t going to go along,” and before any distribution was made he wanted to be sure that Calhoun had released his mechanic’s lien. Calhoun released this lien, relying upon the stop notice to assure him payment of his claim. No request was made of him that he release the stop notice. Subsequently a prorated distribution was made. Calhoun received a check for his share, as well as a cheek for services rendered as a member of the creditor’s committee; offered to return them unless they were tendered as payment of money retained for him under his stop notice ; but did not do so, although he has not cashed either check.
The pretrial conference order did not designate the issues to be tried. By stipulation at the time of such conference the indebtedness of the borrower, Holly Manors, Inc., to Calhoun for dry-wall construction in the sum of $6,525.45 was admitted. Also admitted were allegations in the complaint that this indebtedness was unpaid; that the plaintiff had filed a stop notice requesting that the Association cease further payment to Holly Manors, Inc., from the construction loan fund until his claim had been paid; and that the sum of $49,953.15 was on deposit in that fund at that time.
On appeal the Association makes four contentions, i.e., that
The contention that the “stop notice caught nothing” is based on the fact that Holly Manors, Inc., had defaulted under the terms of the loan agreement and, in accord with the provisions thereof, the Association was entitled to withdraw the remaining funds on deposit with it and credit the same to the obligations secured by its deeds of trust. However, the Association did not withdraw these funds, or credit them upon these obligations. Instead, after the stop notice had been given, it deposited the funds with an escrow holder with instructions to pay the same to trustees for the benefit of creditors providing certain designated conditions were met. There is no basis for the contention that the funds ever were credited to the borrower’s indebtedness. To the contrary, by its pretrial conference stipulation the Association admitted that at the time the stop notice was given, it “held” funds from the proceeds of the loan agreement in the sum of $49,953.15.
The contention that the Association complied with the stop notice is based on the claim that the only obligation imposed upon it thereby was to refrain from making further payments out of the fund to the borrower; that it has made no payments to the borrower since the filing of the notice; and, therefore, has complied fully with its obligation in the premises. In this regard, the complaint alleges that the plaintiff, by his notice, requested that further payments from the construction fund to Holly Manors, Inc., “be ceased” until his claim had been paid. It should be noted, however, that section 1190.1, subdivision (h), does not require the person giving a stop notice to therein request the recipient to withhold further payment of the construction funds in its possession. If the claimant supplements his notice with an appropriate bond, the law imposes upon the party entrusted with those funds the obligation to “withhold from the borrower or other person to whom said owner may be obligated to make payments or advancements out of said fund sufficient money to answer such claim, and any lien that may be filed therefor.” (Code Civ. Proc., § 1190.1, subd. (h).)
We conclude that the “equitable garnishment” referred to in section 1190.1, subdivision (h), may be enforced through an action in equity; that the holder of construction funds may not invalidate the effect of a notice and bond given pursuant to the statutory provisions by thereafter transferring
The contentions that the court erred in not finding that Calhoun agreed to take only his prorata share of the remaining construction funds, and in not finding that he was estopped to take more than such a prorata share, in substance, are contentions that the evidence establishes such findings as a matter of law. A finding of fact is not established as a matter of law unless the record supports no other reasonable conclusion. (Hudson v. Rainville, 46 Cal.2d 474 , 477 [ 297 P.2d 434 ] ; Martinez v. Southern Pacific Co., 45 Cal.2d 244 , 248 [ 288 P.2d 868 ] ; Bowman v. Collins, 181 Cal.App.2d 807 , 810 [ 5 Cal.Rptr. 776 ].) If the evidence offered in support of such a finding is of that character which the trial court is entitled to reject, or if there is substantial evidence to support a contrary finding actually made, a claim of error in failing to make the finding contended for is not sustained by the record.
The trial court found that Calhoun did not agree, either expressly or impliedly, that he would release his stop notice claim or that he would execute a power of attorney to Behymer and Hoffman as proposed. Calhoun’s silence when the Association’s proposal was voted upon at the March 28th creditors’ meeting did not require a finding, as a matter of law, that he assented thereto. “The question of acceptance by silence or acquiescence is a question of fact.” (McAulay v. Jones, 110 Cal.App.2d 302 , 309 [ 242 P.2d 650 ] ; Beatty Safway Scaffold v. Skrable, 180 Cal.App.2d 650 , 655 [ 4 Cal.Rptr. 543 ].)
The appeal by Calhoun is from that part of the judgment denying interest on the unpaid balance due him under his contract. He claims interest on this amount from January 26, 1956, the day when the stop notice was served, relying upon the provisions of section 3287 of the Civil Code that:
“Every person who is entitled to recover damages certain, or capable of being made certain by calculation, and the right to recover which is vested in him upon a particular day, is entitled also to recover interest thereon from that day. ...”
In opposition, the Association relies upon the provisions of section 3288 of the Civil Code that an award of interest is discretionary in “an action for the breach of an obligation not arising from contract, ’’ and contends that these provisions are controlling in the case at bar.
Calhoun’s claim against Holly Manors, Inc., was based on a written contract, under which he agreed to furnish labor and material for dry-wall construction and Holly Manors, Inc., agreed to pay him $33,607 therefor. At the time Calhoun filed his stop notice he had completed his part of the contract; had been paid $27,080.55 on account; and the sum of $6,525.45, the amount specified in the stop notice, remained unpaid.
Where the amount payable under a contract is fixed thereby, interest thereon is recoverable in an action against the promissor from the date the obligation becomes due. (Richter v. Walker, 36 Cal.2d 634 , 646 [ 226 P.2d 593 ] ; Walpole v. Prefab Mfg. Co., 103 Cal.App.2d 472 , 484 [ 230 P.2d 36 ] ; Glens Falls Inclem. Co. v. Perscallo, 96 Cal.App.2d 799 , 803 [ 216 P.2d 567 ].) The “equitable garnishment” effected through stop notice proceedings, like a mechanic’s lien, “is as extensive as the claim which it is intended to protect.’’ (Pacific Mutual Life Ins. Co. v. Fisher, 106 Cal. 224 , 233, 234 [39 P.758].) In the case at bar, this claim included Calhoun’s demand for the amount due him under his contract and also an award of interest in the event he brought an action to enforce such demand. Interest prior to judgment has been awarded in actions to foreclose mechanics’ liens (Meda v. Lawton, 217 Cal. 282 , 285, 286 [ 18 P.2d 655 ] ; Sweet v. Fresno Hotel Co., 174 Cal. 789 , 798 [ 164 P. 788 , Ann. Cas. 1918D 346] ; Macomber v. Bigelow, 126 Cal. 9 , 15 [ 58 P. 312 ]; Pacific Mutual Life Ins. Co. v. Fisher, supra, 106 Cal. 224 ,
The judgment is modified to provide for interest in accordance with this opinion and as so modified, paragraph I thereof shall read as follows:
“That plaintiff have and recover from defendant Huntington Park First Savings & Loan Association the sum of $6525.45 together with interest thereon at the rate of 7% per annum from January 26, 1956 to date hereof. ’ ’
As so modified, the judgment is affirmed. Respondent and cross-appellant Calhoun will recover costs on appeal.
Griffin, P. J., and Shepard, J., concurred.
Cases cited
- Diamond Match Co. v. Silberstein 165 Cal. 282 at 288, at 289 p. 459, p. 460, p. 463
- Hampton v. Christensen 148 Cal. 729 at 740, at 739 p. 459, p. 460
- Weldon v. Superior Court 138 Cal. 427 at 430, at 431 p. 459
- Bates v. County of Santa Barbara 90 Cal. 543 at 548, at 547 p. 459
- L. W. Blinn Lumber Co. v. Pioneer Drainage District 50 Cal.App. 364 at 370 p. 459, p. 460
- Frey v. Superior Court 22 Cal.App. 421 at 422, at 423 p. 459
- Bianchi v. Hughes 124 Cal. 24 at 27, at 28 p. 459, p. 460
- Grigsby v. Ross 138 Cal.App. 757 at 759 p. 459
- Butler v. Ng Chung 160 Cal. 435 at 439 p. 460
- S. Cal. Elec. Co. v. McDonald 178 Cal. 386 at 390 p. 460
- Hudson v. Rainville 46 Cal.2d 474 at 477 p. 460
- Martinez v. Southern Pacific Co. 45 Cal.2d 244 at 248 p. 460
- Bowman v. Collins 181 Cal.App.2d 807 at 810 p. 460
- McAulay v. Jones 110 Cal.App.2d 302 at 309 p. 460
- Beatty Safway Scaffold, Inc. v. Skrable 180 Cal.App.2d 650 at 655 p. 460
- Lusitanian-American Development Co. v. Seaboard Dairy Credit Corp. 1 Cal.2d 121 at 128 p. 461
- City of San Diego v. Cuyamaca Water Co. 209 Cal. 105 at 149 p. 461
- Mercantile Trust Co. v. Sunset Road Oil Co. 176 Cal. 461 at 472 p. 461
- Filipini v. Trobock 134 Cal. 441 at 444 p. 461
- Pike v. Rhinehart 112 Cal.App.2d 530 at 533 p. 461
- Primm v. Primm 46 Cal.2d 690 at 693 p. 462
- Richter v. Walker 36 Cal.2d 634 at 646 p. 462
- Walpole v. Prefab Manufacturing Co. 103 Cal.App.2d 472 at 484 p. 462
- Glens Falls Indemnity Co. v. Perscallo 96 Cal.App.2d 799 at 803 p. 462
- Pacific Mutual Life Insurance Co. v. Fisher 106 Cal. 224 at 233, 234 p. 462
- Meda v. Lawton 217 Cal. 282 at 285, 286 p. 462
- Sweet v. Fresno Hotel Co. 174 Cal. 789 at 798 p. 462
- C.A. Macomber v. L. M. Bigelow 126 Cal. 9 at 15 p. 462