Majority
COUGHLIN, J.
— This is an action by a material-man against a surety on a contractor’s bond to recover the alleged unpaid portion of an indebtedness for materials furnished at the request of the contractor. The ease was heard upon a stipulation of facts, from which it appears that a contractor named Posey agreed to do certain construction work upon property owned by a corporation named C. E. Morris, Inc.; in connection therewith, the defendant insurance company, the respondent herein, as surety, and Posey, as eon-
At this juncture it should be noted that the stipulation of facts contains no statement of the intention of the plaintiffs or the contractor with respect to the transaction involving the endorsement by the plaintiffs and delivery to the contractor of the owner’s cheek which was made payable to both of them, and the simultaneous delivery by the contractor to the plaintiffs of a check in a like amount payable to the latter and drawn on the construction company account.
From the foregoing facts the court drew the following conclusions of law, viz, (1) That the plaintiffs have received payment in full for the materials furnished by them “to” the subject real property at the request of the contractor; and (2) that, in any event, the plaintiffs have waived their right to recover from defendant insurance company “under and pursuant to the terms and provisions” of the surety bond in question.
Judgment was entered in favor of the defendant from which the plaintiffs appeal, contending that the evidence does not support the findings of fact and conclusions of law that they were paid for the materials furnished by them at the request of the contractor and used in the construction work described in the subject surety bond, or that they waived their right to recover from the defendant under that bond. In response thereto and in support of the judgment in its favor, the defendant cites the decisions in Edwards v. Curry, 152 Cal.App.2d 726 [ 313 P.2d 613 ], Westwood Building Materials Co. v. Valdez, 158 Cal.App.2d 107 [ 322 P.2d 79 ], and Petaluma Building Materials, Inc. v. Foremost Properties, Inc., 180 Cal.App.2d 83 [ 4 Cal.Rptr. 268 ]. However, these decisions are not controlling in the case at bar. Although each of the cited eases involved a materialman who had furnished materials at the request of a subcontractor for use in construction work on designated property, and a payment by check drawn in favor of the materialman and the subcontractor, as copayees, which had been endorsed by the materialman and delivered to the subcontractor who retained the entire proceeds therefrom, in each case the action was against the person who had made the payment, i.e., the drawer of the check
In the instant case there is no indication in the stipulation of facts that the $18,525.84 check payable to the contractor and the plaintiffs, insofar as the latter were concerned, was drawn by the owner for any other consideration than the execution and delivery to it of a written waiver of the plaintiffs’ lien rights against the owner’s property. The defendant argues that the stipulation merely indicates one of the considerations for the check. The transaction under consideration involved distinct rights and obligations; the owner was indebted to the contractor upon performance by the latter of his obligations under the construction contract; the contractor was indebted to the plaintiffs for materials furnished by them at his request; and the plaintiffs had a lien against the owner’s property, upon which their materials were used, to secure payment of the contractor’s indebtedness to them. The check in question was given and received as a consideration for a waiver of the plaintiffs’ lien rights against the owner’s property and as a pro tanto payment of the owner’s indebtedness to the contractor. However, the facts which establish the issuance and acceptance of the check for these purposes do not support an inference that the check was given and received in payment of the contractor’s indebtedness to the plaintiffs. It is noteworthy that the stipulation of facts recites that the plaintiffs waived their lien against the owner’s property in consideration of the check and not that they acknowledged satisfaction of or discharged that lien.
A materialman may waive his lien against property which is the subject of construction work for which he has furnished materials without in any way impairing his right to proceed against the surety on a contractor’s bond posted in connection with that work pursuant to the provisions of the mechanic’s lien law, viz., sections 1181 et seq. of the Code of Civil Procedure. (Fraters Glass & Paint Co. v. Southwestern Constr. Co., 200 Cal. 688 , 693 [ 254 P. 1097 ].)
The conditions of a contractor’s bond, such as that under consideration in the instant case, are prescribed by sections 1185.1 and 1200.1 of the Code of Civil Procedure. The subject bond expressly declares that it “is executed for the purpose of complying with the Laws of the State of California as contained in Sections 1181, et seq., Code of Civil Procedure and all acts amendatory thereof”; and that it “shall inure to
“ The burden of proving a particular application of a payment by either the debtor or creditor is on the party claiming that such application was made.” (Hollywood etc. Co. v. John Baskin, Inc., 121 Cal.App.2d 415 , 429 [ 263 P.2d 665 ].)
In the case at bar the burden of proving that the payment by the owner was applied to the debt which the contractor owed the plaintiffs was upon the defendant. The mere fact that the owner drew a check against construction funds
The defendant contends that, nevertheless, by the instant action, the plaintiffs seek to recover on an obligation created by delivery of the construction company’s check to them at the time they relinquished the owner’s cheek to the contractor; that this is not an obligation the payment of which is guaranteed by the subject bond; and, therefore, the judgment denying recovery under the bond should be affirmed, citing the decisions in Cadenasso v. Antonelle, 127 Cal. 382 [ 59 P. 765 ] and People’s Nat. Bank v. Southern Surety Co., 105 Cal.App. 731 [ 288 P. 827 ], in support of this position. The cited cases hold that the repayment of money advanced to a contractor by a materialman is not secured by a contractor’s bond such as the one at bar. The evidence does not support a conclusion that the plaintiffs, by their instant action, seek to recover money advanced by them to the contractor. Under the stipulation of facts before us, on September 2, 1960, the contractor, Posey, an individual, was indebted to the plaintiffs in the sum of $28,000.79 on account of materials furnished to him, of which $18,525.84 is alleged by the plaintiffs to be the reasonable value of materials furnished to the construction work referred to in the subject bond; on October 7,1961, the plaintiffs brought an action against Posey, an individual, and also against Posey Construction Company, Inc., a corporation, as defendants, by filing a complaint which alleged that the defendants therein named were indebted to the plaintiffs therein named in the sum of $29,318.46 on account of equipment and materials furnished to said defendants at the latter’s request, in consideration of which said defendants promised to pay said sum, and thereafter a stipulated judgment was entered in said action directing recovery by the plaintiffs from Posey, an individual, of the sum of $9,474.95, and from Posey, an individual and the construction company, a corporation, jointly and severally, the sum of $18,525.84, which was the alleged reasonable value of the materials furnished to the construction work in question at the request of Posey, the contractor named in the subject bond. Although Posey had given the plaintiffs a check for $18,525.84 drawn on the construction company’s account, the complaint filed against Posey and the corporation did not allege the execution and delivery of this
No contention is made that the amount paid upon the judgment, which the plaintiffs obtained against the contractor and the construction company, was not so allocated as to leave an $8,000 unpaid balance upon that part thereof against the contractor and the construction company jointly and severally. The finding of the court respecting the $8,000 unpaid to the plaintiffs indicates that the amount in question was unpaid on the account for materials furnished by the plaintiffs to the contractor for use in the construction work referred to in the contractor’s bond.
The defendant further contends that, in any event, the plaintiffs have waived their right to recover under the subject bond. This contention was accepted by the trial court, as expressed in its conclusions of law. In support thereof the defendant argues that the plaintiffs violated their duty to it as a surety when they endorsed and surrendered the owner’s
The judgment is reversed with instructions to enter judgment in favor of the plaintiffs in harmony with the views expressed in this opinion.
Griffin, P. J., concurred.
A petition for a rehearing was denied February 4, 1963, and respondent’s petition for a hearing by the Supreme Court was denied March 6, 1963.
Cases cited
- Edwards v. Curry 152 Cal.App.2d 726 p. 654
- Westwood Building Materials Co. v. Valdez 158 Cal.App.2d 107 p. 654
- Petaluma Building Materials, Inc. v. Foremost Properties, Inc. 180 Cal.App.2d 83 p. 654
- Fraters Glass & Paint Co.v. Sw. Construction Co. 200 Cal. 688 at 693 p. 655, p. 659
- Hollywood Wholesale Electric Co. v. John Baskin, Inc. 121 Cal.App.2d 415 at 429 p. 656
- Cadenasso v. Antonelle 127 Cal. 382 p. 657
- Peoples National Bank v. Southern Surety Co. 105 Cal.App. 731 p. 657
- Hammond Lumber Co. v. Richardson Bldg. & Eng'g Co. 209 Cal. 82 at 86 p. 658
- S. W. Towle Lumber Co. v. Anderson 208 Cal. 371 at 374-375 p. 659