1. Action by Lessors for Damages for Breach of Lessee’s Covenant to Make Improvements within a Certain Time—Extension of Time. The lessors in a lease for a term of years, by which the lessee covenanted to make certain improvements within ninety dáys after the commencement of the term, and which imposed upon him the duty of procuring, and conforming to, the approval of the municipal building department, commenced an action, on the expiration of the ninety days, to recover damages for the lessee's failure to perform his covenant. The case being in a condition for taking an inquest, it was agreed that if the lessee should give a mortgage as security for performance, and should within thirty days commence the improvements, with the approval of the building department, and proceed with diligence, payment of the mortgage would not be required. The lessee gave the mortgage, hut the lessors, claiming that an appraisal of the mortgaged premises showed the security to be inadequate, enforced the inquest and entered judgment. The lessee commenced the work within thirty days from the making of the agreement, and having obtained leave to open the judgment, interposed a supplemental answer, setting up the agreement and his compliance therewith. The action was tried, and resulted in a recovery of damages by the lessors, upon a decision that the lessee had not performed the covenant of the lease at the time of the commencement of the action or at the time when the supplemental answer was served. Held, that the recovery was erroneous, in that the decision did not include a determination as to whether the defendant, at the time of the trial, had performed or was performing with diligence the ag'reement extending his time.This action was brought to recover for a breach of covenants contained in a lease made by the plaintiffs, as lessors, to the defendant, as lessee. Originally the complaint embraced three causes of action, but two have been eliminated, and only one remains.
On the 18th day of April, 1894, the plaintiffs, as parties of the first part, as lessors, and the defendant, as party of the second part, as lessee, executed a lease of premises known as Ho. 806 Eighth avenue, in the city of Hew York, for the term of seven years, commencing on the first day of May, 1894, at the yearly rent of $3,250 from the first day of May, 1894, to the first day of May, 1897, and at the yearly rent of $3,500 for the last four years of the term. The lease contained the following covenants : “ And the said party of the second part further covenants and agrees that he will comply with all requirements of the board of health, municipal authorities, police and fire departments of the city of Hew York. And the said party of the second part further covenants and agrees that he will, within ninety days after the commencement of the said term, at his own proper cost and expense, make and complete the alterations and repairs, provided for by the plans and specifications submitted to and approved by the parties of the first part on the 18th day of April, 1894.” The plans and specifications herein specified as executed on the 18tli day of April, 1894, described in detail with drawings the improvements to be made, and concluded as follows: “ All the above work will be done in accordance with the rules and regulations of the building department.”
This action was commenced on the 12th day of September, 1894, and the relief demanded is that the plaintiffs recover the damages they have sustained by reason of the failure of the defendant to complete the alterations and repairs upon the premises provided for in the covenants alluded to. It appears that at the time the action was brought the time within which the alterations were to be completed had expired and that the defendant had not then commenced the repairs or taken' any
After the action had been commenced the defendant made an unsuccessful attempt to procure the approval of the plans by the building department and interposed an answer. The situation then remained unchanged until the 24th day of May, 1895, at which time the case, being upon .the short cause calendar, was moved for trial by the plaintiffs, and, in the absence of the defendant, an inquest was taken and a judgment for damages entered for §8,882.54. Subsequently the default of the defendant' was excused, the judgment opened and the defendant was let in to defend upon giving security to pay any judgment that should be finally entered against him. He then was allowed to serve a supplemental answer. The case was referred to a referee, who, after trial, reported a judgment in favor of the plaintiffs for $2,500 damages.
We think that the learned referee properly construed the lease; that under the covenants the duty devolved upon the lessee to procure the approval of the building department to the plans and specifications agreed upon, and that he undertook to make the improvements in accordance with such plans as modified to meet the requirements of the building department. We also agree with the referee that he adopted the true rule for determining the measure of damages upon the assumption that the situation of the parties remained as disclosed down to the day on which the inquest was taken. We are not, however, satisfied that, in the judgment directed by him, exact justice has been done the "defendant. It is true he was in default and had, doubtless, failed to keep and perform his repeated promises. But, notwithstanding this, he is entitled to such rights as the law affords and should be called upon to pay only such damages as he has caused by his acts or neglects.
On the morning of the 24th of May, 1895, before the inquest was taken, the parties met in the court room and there had a conversation with reference to a settlement. It was then arranged that the defendant should give the plaintiffs a bond and mortgage for $5,000 on property owned by
The situation of the defendant was then embarrassing in the extreme. He was, figuratively speaking, between the upper and nether millstones. He had given a bond and mortgage in the sum of $5,000 absolute in form, as security that he would commence work upon the contemplated building at
The defendant, in order to sustain his defense under the agreement of May 24tli, 1895, was bound to show that he commenced operation within thirty days; that he procured the consent of the building department, and that he proceeded with the work with reasonable diligence. For the purpose of establishing reasonable diligence lie had the right to show the delays occasioned by the building department or by the inspectors of that department having charge of the work. Evidence of this character was, in a number of instances, ruled out under the exception of the defendant. It is true that the referee, near the end of the defendant’s testimony, changed his ruling with reference to this class of evidence as to the witness Watson, but as to the other witnesses the ruling remained unchanged and their evidence was not received.
The plaintiffs, as we have seen, entered judgment upon the inquest, notwithstanding the agreement of May 24th. They justify their action in this regard upon the claim that the appraisal showed the premises to be incumbered and not worth the amount of the defendant’s mortgage to them. They, however, did not present as a witness the person who made the appraisal, so that we have not the advantage of his testimony. The only evidence we have upon the subject is the oral report made to them. The evidence about the appraisal was, therefore, hearsay. For the purpose of rebutting it the defendant undertook to show by a builder the fair market value of the 97th street property covered by the mortgage. This was objected to as incompetent, immaterial and irrelevant. The objection was sustained and an exception taken. We think it was competent and material. It might have shown that the property was of ample value to secure the payment of the mortgage, and that the plaintiffs were not justified in terminating the agreement made on the 24th of May, and entering the judgment taken upon the inquest.
It is claimed that under the will of Henry E. Davies, deceased, the plaintiffs, as trustees, have no power of sale. To establish this the defendant offered a copy of the will produced by the plaintiffs in evidence, but the same was excluded by the court.
Inasmuch as no exception was taken to this ruling no question is presented for our review upon this branch of the case.
For the- other reasons stated, the judgment should be reversed and a new trial ordered, with costs to abide the event.
All concur, except Gray, J., not voting.
Judgment reversed, etc.
Cases cited
- Davies v. Clark 10 App. Div. 68 p. 392
- Grant v. Johnson 5 N. Y. 247 p. 393
- Giles v. O'Toole 4 Barb. 261 p. 393
- Lawrence v. Wardwell 6 Barb. 423 p. 393
- Walker v. Swayzee 3 Abb. Pr. 136 p. 393
- Flynn v. Hatton 43 How. Pr. 333 p. 393
- Mayor v. Second Avenue Railroad 102 N. Y. 572 p. 393
- Powers v. Shepard 48 N. Y. 540 p. 393
- Smith v. City of Albany 7 Lans. 14 p. 393
- Smith v. City of Albany 61 N. Y. 444 p. 393
- Nichols v. Mase 94 N. Y. 160 p. 393
- Haden v. Coleman 73 N. Y. 567 p. 393
- National Bank of Virginia v. Mills 120 N. Y. 638 p. 393
- Flaherty v. Miner 123 N. Y. 382 p. 393
- Heeter v. Eckstein 50 How. Pr. 445 p. 393
- Tompkins v. Dudley 25 N. Y. 272 p. 394
- Ward v. Hudson River Building Co. 125 N. Y. 230 p. 394
- Beebe v. Johnson 19 Wend. 500 p. 394
- Booth v. Spuyten Duyvil Rolling Mill Co. 60 N.Y. 487 p. 394
- Dermott v. Jones 2 Wall. 1 p. 394
- Chamberlain v. Parker 45 N. Y. 569 p. 394
- Agate v. Lowenbein 57 N. Y. 604 p. 394
- Robinson v. Kime 70 N. Y. 147 p. 394
- Robinson v. Wheeler 25 N. Y. 252 p. 394
- Austin v. Hudson River Railroad 25 N. Y. 334 p. 394
- Kernochan v. New York Elevated Railroad 128 N. Y. 559 p. 394
- Atwood v. Norton 27 Barb. 638 p. 394
- Colby v. Reed 99 U. S. 560 p. 394
- Ganson v. Tifft 71 N. Y. 48 p. 394
- Livermore v. Northrup 44 N. Y. 107 p. 394