Majority
Headnote
Contract — Stipulated Test op Machinery Excused when the Other Party Failed to Furnish the Power as Agreed. Where a contractor agreed to furnish and erect air propellers for removing smoke from the tempering room of a manufacturing company, to run with power furnished hy the company, the work of construction to he performed to the satisfaction of the engineer of the company, and subject to its approbation after a thirty days’ trial, and the contractor having obtained the certificate of the engineer that the apparatus was properly construed^, but such trial could not be made because the company failed to fui^pL the power, the contractor is relieved from such test and is entitled to recover the contract price, under the rule that where the obligation of one party to perform is dependent upon prior action by the other, the refusal of the latter to perform dispenses with the obligation of the former.This action was tried before the court, a jury having been waived. Both parties presented requests to find. Findings were made to the effect that on or about the fifth day of December, 1890, the plaintiffs contracted with the defendant to furnish and erect in the tempering room of its
The defendant requested the court to find that the plaintiffs had not performed their contract, in that they omitted to furnish the necessary shafting and pulleys to communicate sufficient power to the shafting in defendant’s tempering room, by reason wjiereof the apparatus had not effected the removal of smoke from the room, and that the probationary period of thirty days provided for in the contract had not at the time of the commencement of the action actually begun. This request the court refused and instead found that the defendant neglected to furnish sufficient power to drive the propellers ; that the work of construction had been done to the satisfaction of the mechanical engineer whose certifícate of approval was provided for in the contract; and that he had so certified, but was prevented from giving his certificate of approval as to the effectiveness of the propeller's in removing smoke by reason of the defendant’s failure to supply the necessary power to run the propellers.
As this action was tried in February, 1894, the Code as it then existed governs the practice, and the appellant is right in insisting that a refusal to make any findings whatever upon a question of fact material to the issue, where a request to find was seasonably made, was a ruling upon a question of law and an exception taken thereto presents a question re viewable by this court. (Kennedy v. Porter, 109 N. Y. 526 .) Complaint cannot be made of the refusal of the court to make the finding in its entirety, because it appears in other findings that
At the outset of the negotiations, Mr. Wolff, who had been the defendant’s mechanical engineer, requested the plaintiffs’ representative to meet him at the defendant’s factory to consider appliances for removing smoke from its tempering room. The power in the factory had all been put in under the direction of Wolff, who, after consultation with "an officer of the defendant company and the plaintiffs’ representative, decided to take the power from a certain line of shafting, the only line of shafting in the tempering room; the plaintiffs made the necessary connection with the shafting at the point indicated, and so completed their work in j>oint of construction as to meet the approval of Wolff; but when the fans were started the defendant’s shafting broke down, and a controversy at once arose between the parties as to whether the plaintiffs were obliged to furnish additional, or, if necessary, entirely new shafting to run the propellers, or whether they had performed their work when they made connection witli the shafting in the defendant’s tempering room at the point where it had been decided to make it when the negotiations were entered into which resulted in the contract. After an examination of the evidence on that subject we have reached the conclusion that the trial court was warranted in finding that the plaintiffs had performed their part of the-contract when
How, it is true, as the appellant insists, that the propellers have not removed the smoke from the tempering room as the plaintiffs contracted they should, nor has the defendant, after thirty days’ trial, approved of them, for there has not been a thirty days’ trial, the propellers not having been run at all. But the plaintiffs obtained the certificate of the engineer that the apparatus had been properly constructed, and in view of the finding of the court that operation was prevented only by the failure of the defendant to furnish power as it had contracted to, they did all that they could do until after performance of the obligation of the defendant to furnish the needed power. The situation, therefore, is within that principle of law applicable to the construction of contracts, that whén the obligation to perforin some act by one party is dependent upon some prior action by the other- party to the contract, the refusal of the latter to perform dispenses with the obligation of the former. Applying that principle, our conclusion is that the court below was right in holding that the plaintiffs, having constructed the appliances to the satisfaction of the engineer, the defendant could not refuse payment of the contract price on the ground that the propellers had not removed the smoke from the tempering room for the period of thirty days or to its satisfaction, such ground being supplied through its own failure to furnish the necessary power as agreed.
The judgment should be affirmed, with costs.
Gray, O’Brien, Haight, Landon, Cullen and Werner, <JJ., concur.
Judgment affirmed.
Cases cited
- Engelhorn v. Reitlinger 122 N. Y. 76 at 81 p. 347
- Crouch v. Gutmann 134 N. Y. 45 p. 347
- Romeyn v. Sickles 108 N. Y. 650 p. 347
- Schenectady & Saratoga Plank Road Co. v. Thatcher 11 N. Y. 102 p. 348
- McCotter v. Hooker 8 N. Y. 497 p. 348
- Jackson, ex rel. Walton v. Leggett 7 Wend. 377 p. 348
- Tiffany v. St. John 65 N. Y. 314 p. 348
- Kennedy v. Porter 109 N. Y. 526 p. 348, p. 349
- Bogardus v. New York Life Insurance 101 N. Y. 328 p. 348
- Gallagher v. Nichols 60 N. Y. 438 at 448 p. 348
- Wyckoff v. Meyers 44 N. Y. 143 p. 348
- Mansfield v. New York Central & Hudson River Railroad 102 N. Y. 205 p. 348
- Nolan v. Whitney 88 N. Y. 648 p. 348
- Heckmann v. Pinkney 81 N. Y. 211 p. 348