Majority
Headnote
New York city — contract —• Rapid Transit Act — no ground for application of special rules of construction to contract made by Public Service Commission under Rapid Transit Act — city of New York liable to contractor for damages caused by delay of engineer of Commission in performing his duties — sufficiency of evidence to sustain finding that plaintiff is entitled to recover for increased cost of work — interest on percentages of moneys earned but retained by city improperly allowed — evidence of payrolls of contractor properly received — loss from elimination of work provided for in contract properly allowed contractor —■ no damages from over-estimation where contractor was warned estimated quantities were approximate.The Litchfield Construction Company entered into a contract in May, 1915, for the construction of certain sections of a subway or underground railroad, part of a route adopted by Rapid Transit Railway Commissioners for the city of New York in the year 1905. The contract called for the completion of the work sufficient to permit railroad operation by March 26, 1917, and the entire completion of the work by July 26, 1917. ' In fact, the work was ready for railroad operation only in March, 1919, and was entirely completed only in May, 1919. After completion of the work the plaintiffs brought this action to recover moneys which they claim are due to the Litchfield Construction Company from the city of New York under the provisions of the contract, and also to recover damages which they allege have been caused by breach of contract on the part of the city.
The plaintiffs’ claims embrace numerous separate items. The trial judge directed a verdict in their favor as to some of the items where there was no dispute as to the facts. Where claim rested upon disputed facts, the jury found in favor of the plaintiffs. Upon appeal to the Appellate Division the judgment was reversed as to some of the plaintiffs’ claims and affirmed as to others. Since the defendant has not appealed from the judgment we may review only the claims of the plaintiffs for which redress has been denied. The plaintiffs claim that delay in completing the railroad was due solely to the failure of the engineer of the Public Service Commission to perform at stipulated times the duties imposed upon him under the terms of the contract. For consequent damages they seek to impose liability upon the city. The city denies such liability and has retained, and
The jury has resolved the dispute in favor of the plaintiffs. It has found that the delay in the work was caused solely by the failure of the engineer to carry out promptly, and in strict accordance with the terms of the contract, the duties which the contracting parties have agreed he should perform and that this failure has increased the cost of the work and caused damage to the contractor in the sum of $813,000. As a result, the counterclaim of the city of New York was dismissed by the trial court and the judgment in favor of the plaintiffs, entered thereafter, includes the damages so found and also the sum of $71,090.15 payable under the terms of the contract with interest from December 31, 1919.
The contract purports to be made “ between The City of New York, hereinafter called the City, acting by the Public Service Commission for the First District, hereinafter called the Commission, party of the first part, and Litchfield Construction Co., a corporation organized and existing under the laws of the State of New York, hereinafter called the Contractor, party of the second part.” The Public Service Commission was given authority, subject to certain limitations, to make such a contract “ for and in behalf of the City of New York.” (Rapid Transit Act, section 26; Laws 1891, ch. 4.) The Commission has made this contract pursuant to the powers so given. The contractor under the terms of the contract agreed “ to construct the part hereinafter described of a Rapid Transit Railroad with its
Concededly the work could not be finished within the required time unless promptly begun and steadily and efficiently prosecuted. Even where the contract is silent as to the time within which the engineer must act, duty may be implied under such circumstances that he should act with due promptness, and not by delay or other act of commission or omission unreasonably hinder progress. In regard to the furnishing of working drawings by the engineer and approval by him of shop drawings submitted by the contractor, the contract expressly fixes the time during which he must act. “ The first of these working drawings will be given to the contractor within thirty (30) days after this contract is delivered and the remainder from time to time as may be reasonably and necessarily required by the contractor, and the contractor shall promptly upon the delivery of this contract furnish a written statement to the -engineer showing the order in which he desires the working drawings to facilitate the prosecution of his work, and this order.' will be followed so far as reasonably practicable and"' necessary.” (Specifications, section 4.) Again the contract provides that “ no work called for by said working or shop drawings shall be done until the approval of the engineer be obtained, which must be given or refused within twenty (20) working days after delivery to him at his office of such drawings in duplicate.” The plaintiffs claim that the engineer gave the contractor the first of the working drawings more than thirty days after the contract was delivered, and failed to give the contractor the remainder of the drawings from time to time as they were reasonably and necessarily required, and also failed to approve within reasonable time the shop or detailed drawings for the doing of the work.
The Appellate Division has not held that there was no evidence to sustain the findings. It has decided as a matter of law that no liability rests upon the city for damages caused to the contractor by any delay of the engineer in carrying out his duties. It bases its conclusion in favor of the city upon the view that the engineer of the Public Service Commission acts in the performance of his duties as an officer of the State and not as an agent of the city. The decision is in accord with the opinion of the Appellate Division in the case of Degnon Contracting Co. v. City of New York ( 202 App. Div. 390 ). Upon appeal to this court that decision was affirmed, but on other ground. (Reported 235 N. Y. 481 , 486.) The question of liability of the city for misfeasance or non-feasance on the part of the engineer was expressly left undecided. “ We hold this conclusion even though we assume, without deciding it, that the city was liable for damages caused by the neglect of an engineer in the employ and under the control of the
The Public Service Commissioners are not city officers. “ Rapid transit for the city of New York has, for many years, been a matter of public interest, affecting not only the people of that city, but of the whole State. It has been generally regarded as a State affair.” (Matter of McAneny v. Board of Estimate, 232 N. Y. 377 , 393.) The Rapid Transit Act which conferred power upon State officers to enter into a contract for the construction of a rapid transit railroad “ for and in behalf ” of the city embodies a recognition of State interest in the matter. Nevertheless the construction of a rapid transit railroad like the building of streets or highways constitutes a “city purpose.” (Sun Publishing Association v. Mayor, etc., 152 N. Y. 257 .) In constructing such a railroad, the city acts not as sovereign but as proprietor. (Matter of Rapid Transit Commissioners, 197 N. Y. 81 .) The Commissioners are the agency created by the State to make contracts for the construction of such railroads in behalf of the city. (Admiral Realty Co. v. City of New York, 206 N. Y. 110 .)
It has not been questioned that the Public Service Commissioners could bind the city to pay for the railroad in accordance with the terms of the contract made in its behalf. In the cases cited above, and in many others, this court has decided directly or indirectly that such contractual liability may be imposed on the city. It is said, however, that the city has not agreed to pay damages for non-performance of duties by the engineer, and that it cannot be held responsible for his misfeasance or nonfeasance on the theory of respondeat superior because it never appointed him its agent. His powers and duties, it is said, devolve on him as employee of a State Commission and are not conferred upon him by the city; and the State has not made the Commission or its employees agents of the city except perhaps for the limited
The Rapid Transit Act does not compel the city of New York to construct rapid transit railroads at the expense of the city for the benefit of the people of the State. It merely regulates the manner in which such railroads shall be laid out and constructed after the city or the voters of the city have decided that such railroads shall be constructed. (Sun Publishing Company v. Mayor, etc., supra; Matter of Rapid Transit R. R. Commissioners, supra.) Though the contract must be made by State officers acting for and in behalf of the city, yet city officers must approve both its form and substance before it becomes effective. “ All such contracts must before execution be approved as to form by the corporation counsel, or other chief legal adviser of such city.” (Rapid Transit Act, sec. 36.) Consent of the board of estimate is required before the contract may be made. (Section 37.) These and other provisions scattered through the Rapid Transit Act show that a contract made in accordance therewith is in real sense the voluntary contract of the city, and that city officers share, at least to some extent, with State officers,
We have pointed out that duty to act with promptness is imposed upon the engineer by express and by implied terms of the contract. Question still remains whether under a fair construction of the contract, the city undertook that the engineer would perform that duty. The answer to that question is hardly doubtful. In the case of Degnon Contracting Co. v. City of New York ( 235 N. Y. 481 ) this court in construing similar contracts stated: “ The defendant by the contracts thus executed undertook to furnish certain plans for the steel work through engineers whom the Public Service Commission solely appointed and controlled.” The undertaking to furnish these plans is inseparably connected with provision of the contract fixing the time and manner in which such plans must be furnished. Argument that, since the engineer was not the employee of the city, provision that he shall furnish the plans and drawings for the work should not be construed as impliedly .creating an obligation on the part of the city, ignores the relations of the parties and the evident intention of the contract. The contractor expressly agrees to perform work according to the contract and the specifications which are part of the contract. The specifications contain express statements that the engineer shall perform certain functions in specified manner. Unless the engineer does so the contractor cannot perform his contract. The contractor promises to perform because he has assurance in the contract itself that the engineer will act in prescribed manner. That assurance is given him by the city as the ■ basis of the contract and in giving that assurance the
• The Appellate Division has not passed upon the question whether the evidence in this case sustains the finding that delay by the engineer in furnishing drawings and approving plans has caused damage to the plaintiff in the sum of $813,000. It has affirmed the judgment in so far as it dismisses the counterclaim and permits recovery of the sums of money, payable under the contract, which the defendant has retained. Those parts of the judgment rest.upon a finding that completion of the work was delayed by fault of the engineer and right to payment of stipulated damages thereby lost to the city. (Mosler Safe Co. v. Maiden Lane Safe Deposit Co., 199 N. Y. 479 .) We may not review this finding after it has been unanimously affirmed by the Appellate Division. No finding as to the damage caused by the engineer’s default or as to the length of time such default continued is necessary to sustain those parts of the judgment which have been affirmed. We must, therefore, examine the record to determine whether the evidence is sufficient to show that delay in completing the work for almost two years beyond the contract time, and damage of over $800,000 was caused by the engineer’s default.
Under the contract the engineer was bound to furnish the first of the working drawings within thirty days of the delivery of the contract. We have already pointed out that the undisputed evidence shows that the drawings
The city urges that the contract allowed the contractor choice of method of construction, and that the city may not be held liable for damage caused by the contractor’s choice of an uneconomical method. If option provided by the contract was in fact left open to .the contractor, he may not complain because his' choice of method caused him loss. In this case the jury has found upon sufficient evidence that the option was not left open. Choice of method was dictated by necessity of proceeding with the work without steel, since no steel was then available. An unbroken chain of cause and effect leads from the delay of the engineer in furnishing drawings to the adoption by the contractor of method of construction more expensive than would have been used if no such delay had occurred, and damage may be traced directly to the original default. There is more ground for contention that even though delay by the engineer in. furnishing the working drawings naturally caused some delay in completing the work, other cause of delay also, intervened and that at least in part the work would have been incomplete at the outbreak of the war even though the structural steel had been on hand when the work began. Undoubtedly other causes not contemplated when the contract was made may have intervened to delay the work to some extent. The question underlying recovery by the contractor for the entire increased cost of completing the work after April, 1917, is whether the work would have been completed at that time but for delay occasioned by the engineer. Otherwise, of course,
If the contract had been completed within the contract period the city would have been compelled to pay to the contractor the full contract price before January 1st, 1918. At that date the contract was incomplete, and the city retained the sum of $114,896 out of moneys actually earned before that time. At the end of each month thereafter the city was bound to make payment of moneys earned during the progress of the work, subject to its right to retain an agreed percentage thereof. The amounts so retained at the end of each month till the end of the work varied from $129,000 to $69,000. Interest on the sums so retained till December 31st, 1919, the date when plaintiffs filed their claims with the comptroller, amounts to $11,094.18. The Appellate Division has correctly held that the plaintiffs were not entitled to recover such interest. There is no claim that all moneys were not paid as provided by the contract as the work progressed. The city had the right to retain a percentage of the moneys earned. The contractor became entitled to receive the retained percentage only when it fully completed the work. Delays by the engineer in turn
The city urges and the Appellate Division has held that even if the evidence is sufficient to sustain the finding of damages in favor of the plaintiffs, a new trial is necessary “ because of the improper admission in evidence of the payrolls of the contractor, because proof necessary to their admission was lacking.” The plaintiffs proved their damages by showing the actual cost of completing the work after April, 1917, and the estimated amount the . same work would have cost if performed during the contract period.- They proved payment of actual cost by checks and vouchers. A great mass of
These payrolls were kept in the usual course of business by employees of the contractor. Checks and vouchers show that the contractor paid its workmen in accordance with the lime they worked as shown on the payrolls. Every person who made up these payrolls was produced or his absence properly accounted for. These payrolls were made up from timesheets kept by timekeepers. These timekeepers were also produced or their absence accounted for. The timekeepers testified in effect that they checked up the timesheets during the day, and when they left the work at the close of the day they checked the names of the men who then came to the work on the night shifts. Cross-examination elicited testimony that others checked the time of the night shifts while they were working and when they left at night. The men who checked the time of the night shifts during the night were not produced. There is no question that foundation for the introduction in evidence of the payrolls was sufficiently laid according to the strictest and most technical rules of evidence, in so far as they were made up from timesheets for workers during the day. It is said that without the oral testimony of the men who checked the time of the workers on the night shifts, the payrolls were inadmissible, under authority of the case of Mayor, etc., of New York v. Second Avenue R. R. Co. ( 102 N. Y. 572 ).
The documentary evidence, books, checks, voucher^
Two other claims for damages caused by alleged breach of contract on the part of the city still require consideration.
The section of the railroad which the contractor agreed
The invitation to contractors to bid on the contract for the construction of the railroad included a statement of the estimated approximate quantities of the various classes of work which would be required for performance of the contract. These estimated quantities were thirteen per cent higher than the work actually required in the performance of the contract. The contractors were warned that the estimated quantities were “ approximate
Grant of extra allowance rests within the discretion of the courts below. We may not interfere with such discretion.
For these reasons the judgment of the Appellate Division should be modified in accordance with this opinion and as modified affirmed, with costs to the appellant in this court and in the Appellate Division.
His cock, Ch. J., Cardozo, Pound, McLaughlin, Crane and Andrews, JJ., concur.
Judgment accordingly.
Cases cited
- Maxmilian v. Mayor 62 N. Y. 160 p. 254
- Oakes Manufacturing Co. v. City of New York 206 N. Y. 221 p. 254
- Canavan v. City of Mechanicville 229 N. Y. 473 p. 254
- In re Board of Rapid Transit Railroad 197 N. Y. 81 p. 254, p. 263
- Sun Printing & Publishing Ass'n v. Mayor of New York 152 N. Y. 257 p. 254, p. 256, p. 257, p. 263
- People ex rel. Dunkirk, Warren & Pittsburgh Railroad v. Batchellor 53 N. Y. 128 p. 254
- Admiral Realty Co. v. City of New York 206 N. Y. 110 p. 254, p. 256, p. 257, p. 263
- Crowley v. Lewis 239 N. Y. 264 p. 254
- Mayor of New York v. Tenth National Bank 111 N. Y. 446 p. 254
- Walsh v. Mayor of New York 107 N. Y. 220 p. 254
- Horton v. Andrus 191 N. Y. 231 p. 254
- Peterson v. City of New York 205 N. Y. 323 p. 254, p. 255, p. 273
- Genovese v. Third Avenue Railroad 13 App. Div. 412 p. 254, p. 255
- Borough Construction Co. v. City of New York 200 N. Y. 149 p. 254
- Delafield v. Village of Westfield 41 App. Div. 24 p. 254
- Johnson v. City of New York 231 N. Y. 564 p. 254
- Barnum v. Williams 115 App. Div. 694 p. 254
- Mansfield v. New York Central & Hudson River Railroad 102 N. Y. 205 p. 254
- People ex rel. Cranford Co. v. Willcox 207 N. Y. 743 p. 255
- People ex rel. Rapid Transit Subway Construction Co. v. Craven 210 N. Y. 443 p. 255
- Kinser Construction Co. v. State 204 N. Y. 381 p. 255
- Hollerbach v. United States 233 U. S. 165 p. 255
- United States v. Atlantic Dredging Co. 253 U. S. 1 p. 255
- McGovern v. City of New York 235 N. Y. 275 p. 255
- Taylor v. Mayor of New York 67 N. Y. 87 p. 255, p. 258
- Sweeny v. City of New York 173 N. Y. 414 p. 255, p. 258
- O'Keeffe v. City of New York 176 N. Y. 297 p. 255, p. 258
- Smith v. Board of Education 208 N. Y. 84 p. 255, p. 258
- Blackwell v. Finlay 233 N. Y. 361 p. 255
- Griffin v. Colver 16 N. Y. 489 p. 255
- Mortimer v. Otto 206 N. Y. 89 p. 255
- John A. Roebling's Sons Co. v. City of New York 110 App. Div. 366 p. 255
- Bradley v. McDonald 218 N. Y. 351 p. 255
- City of New York v. Interborough Rapid Transit Co. 236 N. Y. 557 p. 256
- Rapid Transit Subway Construction Co. v. Craig 233 N. Y. 544 p. 256
- McAneny v. Board of Estimate & Apportionment 232 N. Y. 377 at 393 p. 256, p. 257, p. 263
- Schieffelin v. Hylan 227 N. Y. 593 p. 256
- McGovern v. City of New York 234 N. Y. 377 p. 256
- Hall v. Schiff 230 N. Y. 554 p. 256
- Wines v. Mayor of New York 70 N. Y. 613 p. 256
- Dunham v. Townshend 118 N. Y. 281 p. 256
- In re Cooper 93 N. Y. 507 p. 256
- Stemmler v. Mayor of New York 179 N. Y. 473 p. 256
- In re the City of New York 218 N. Y. 274 p. 256
- Sun Printing & Publishing Ass'n v. Mayor of New York 8 App. Div. 230 p. 257
- In re the Continental Guaranty Corp. v. Craig 240 N. Y. 354 p. 257
- People v. Crane 214 N. Y. 154 p. 257
- Heim v. McCall 239 U. S. 175 p. 257
- Mayor v. Second Avenue Railroad 102 N. Y. 572 p. 257, p. 271
- Pneumatic Signal Co. v. Texas & Pacific Railway Co. 216 N. Y. 374 p. 257
- Cameron-Hawn Realty Co. v. City of Albany 207 N. Y. 377 p. 257
- Allen v. City of Oneida 210 N. Y. 496 p. 257
- Snare & Triest Co. v. City of New York 233 N. Y. 528 p. 257
- Leary v. City of Watervliet 222 N. Y. 337 p. 257
- Semper v. Duffey 227 N. Y. 151 p. 257
- Degnon Contracting Co. v. City of New York 235 N. Y. 481 at 486 p. 262, p. 265
- Mosler Safe Co. v. Maiden Lane Safe Deposit Co. 199 N. Y. 479 p. 266
- McMaster v. State 108 N. Y. 542 p. 273