Majority
Headnote
1. Damages (§ 80*)—Breach of Contract—Liquidated Damages.It is not necessary to the disposition of the motion for a new trial herein that it should be finally determined whether the per diem sums contracted to be paid in case of failure to complete within the stipulated time are to be regarded as liquidated damages or
“In case the completion of the vessels as aforesaid shall be delayed beyond the periods herein prescribed, deductions may, in the discretion of the Secretary of the Navy, be made from the contract price of each vessel so delayed at the rate of $25 a day, excepting Sundays, during the first month’s delay, and thereafter at the rate of $75 a day, excepting Sundays, during the continuance of such delay.”
In the company’s contract with Nixon it was provided that, in the event of the work being delayed by general strikes over which Nixon had no control, the company would “take the same into consideration in enforcing said liquidated damages for delays”; it being understood that Nixon should use his best efforts in assisting the company to obtain extension of time from the government. As a matter of fact, various extensions of time were obtained by Nixon for the company from the government, and, when the boats were finally delivered and accepted after their trial trips, the contract prices were paid in full to the company, without deduction of any kind; the extensions obtained by Nixon having carried the times for performance-of the main contract beyond the dates of actual delivery. Regardless of this, the company seeks -to hold Nixon for the delay in delivery under his subcontract.
While the payment to the government in case of delay was called a “penalty,” that language, of course, is not controlling,- any more than
But, even if the sums provided for in case of delay in completion be regarded as liquidated damages, and not as penalties, I am of the opinion that so much" of the verdict herein as awards plaintiff $30,000 damages, for failure to deliver the boats in time cannot stand. Plaintiff claimed the sum of $68,000 as the aggregate of the amounts due from defendant, computed at the per diem rates for delays on each boat. It appeared upon the trial that, after the time set for completion and delivery, certain “purchase orders,” also referred to as “extra orders,” were given, the result of which, it was claimed, was to still further delay the completion of the boats. "Plaintiff denied that the orders caused any such delay. This issue was left to the jury, which found for the plaintiff upon this count to the extent only of $30,000, thus determining that more than one-half of the delay in completion was due to plaintiff’s own acts, which finding found ample support in testimony as to the serious "character of some of the changes made, involving much loss of time. It is well settled that, where one party to a contract is himself responsible in whole dr in part for a delay in completion, and has by his acts waived completion at the date fixed by the contract, the provisión for' liquidated damages is abrogated, the question becomes one of completion within a reasonable time under all the circumstances, and actual damages only can be recovered; there being no apportionment possible of liquidated damages. Willis v. Webster, 1 App. Div. 301 , 37 N. Y. Supp. 354 ; Dodd v. Churton, 1 Q. B. D. 562; 19 Am. & Eng. Encyc. of Law (2d Ed.) 423; Thilemann v. City of New York, 82 App. Div. 136 , 81 N. Y. Supp. 773 ; Callanan Road Improvement Co. v. Village of Oneonta, 117 App. Div. 332 , 101 N. Y. Supp. 1056 ; Cornell v. Standard Oil Co., 91 App. Div. 345 , 86 N. Y. Supp. 633 ; Dady v. Mayor, 57 Hun, 456 , 10 N. Y. Supp. 819 ; Weeks v. Little, 89 N. Y. 566 ; Smith v. Gugerty, 4 Barb. (N. Y.). 614;
The remaining items of plaintiff’s recovery are based on a different claim and state of facts. They are amounts for which plaintiff - claims to be entitled to be reimbursed by reason either of an oral agreement or under the terms of the written contract. The disputed questions of fact arising with respect thereto have been resolved by the jury in plaintiff’s favor. The fact that it did not recover the full amount of its claim thereupon furnishes no ground for setting aside the recovery. There was a fair issue presented, not only as to the making of the oral agreement, but also as to the amounts actually expended and as to how much thereof was properly chargeable against defendant. I see no reason for disturbing the jury’s findings in these particulars.
The motion for a new trial will therefore be granted, unless plaintiff within 10 days files a stipulation consenting to the reduction of said verdict to the sum of $18,482.41, in which event the motion will be denied, without costs.
Judgment accordingly.