Majority
Headnote
1. Contracts (§ 303[2] )—Building—Contracts—Termination.[1] On the 22d_day of August, 1906, the plaintiff, a domestic corporation engaged in building construction, and the appellant, made a contract in writing, by which plaintiff undertook to erect on premises owned by appellant situate at the northeast corner of Sixty-Fourth street and Broadway, borough of Manhattan, New York, a six-story re-enforced concrete building in accordance with specifiations and drawings theretofore prepared by one F. M. Andrews, an architect, under whose direction the work was to be done. The main floor of the building was to consist of stores, and the remainder of the building was to be used as a garage. The contract provided that the building was to be completely finished and ready for occupancy on or before the 1st day of July, 1907, and, in default thereof, the respondent was to pay the appellant as liquidated damages the sum of $200 for each day thereafter until the building was completed and ready for occupancy. The respondent failed to complete the building within the time specified in the contract, and, in fact, had not completed the excavation work at one corner of the plot at that time, although the excavation work had been finished and some of the concrete work done on other parts of the plot. The contract contained the usual provision that should the contractor at any time refuse or neglect to supply a sufficient number of skilled workmen, or sufficient materials of proper quality, or fail in any other respect to prosecute the work promptly and diligently or to perform its agreement, the owner should be at liberty, on such neglect, refusal, or failure being certified by the architect, after three days’ notice in writing to the contractor, to provide the necessary labor or materials at the expense of the contractor; and it was further provided that the owner should be at liberty to terminate the employment of the contractor and to take possession of the work for the purpose of completing it for the account of the contractor as therein provided, should the architect certify that such refusal, neglect, or failure on the part of the contractor constituted sufficient ground for such action. On the 2d day of July, 1907, Maynicke & Franlce, architects, representing the owner, wrote respondent a letter setting out the status of the work on the day before, which was the day on which the work should have been completed, and demanding that the contractor display greater energy to the extent of working nights, and drawing .attention to the fact that the owner would suffer heavy financial loss on account of the delay, and that the contract spoke for itself on that point. The contractor remained in charge of the work, making slow progress, however, without interruption until the 10th day of March, 1908, when Maynicke & Franke, in behalf of the owner, demanded of Andrews that he issue a certificate authorizing the owner to terminate the contract. This was refused, but on the day following the archi
The learned counsel for the appellant concedes that the contract was not lawfully terminated pursuant to its provisions entitling his
[2] The rule is well settled that the owner has a common-law right to cancel the contract after the contractor, without fault on the part of the owner, fails to perform within the time specified for performance, or within the time to which by mutual agreement performance has been extended (Frenkel v. Friedmann, 199 N. Y. 351 , 92 N.
[3] The rule is well settled that, where the time of performance has been waived and the contractor has been permitted to fully perform, the owner cannot interpose the failure of the contractor to perform within the time required as a defense to the action to recover the contract price of the work, but he may counterclaim his damages or sue therefor by an independent action. Deeves & Son v. Manhattan Life Ins. Co., 195 N. Y. 324 , 88 N. E. 395 ; Reading Hdw. Co., v. City of New York, 129 App. Div. 292 , 113 N. Y. Supp. 331 ; Raymore v. Pfotenshauer-Nesbit Co., 139 App. Div. 126 , 123 N. Y. Supp. 875 .
[4] The owner contends that he was entitled to recover the liquidated damages, and the learned counsel for the respondent at one stage of his argument, at least, accepts that theory for he contends that the owner was in part responsible for the delay, and that, therefore, the court will not apportion liquidated damages, which is the rule. Mosler Safe Co. v. Maiden Lane S. D. Co., 199 N. Y. 479 , 93 N. E. 81 . The court, however, in Mosler Safe Co. v. Maiden Lane S. D. Co., supra, held that where both parties are responsible for delay by which the time fixed for performance has passed, and the liquidated damage clause for that reason cannot be enforced, it is the duty of the contractor to complete within a reasonable time after crediting the owner’s delay, and in his failure so to do the owner may recover his actual damage. In the case at bar, the owner acquiesced in the continuance of the work by the contractor after the time for completion by demanding, through his architect, a greater degree of energy and expedition, and he never gave the contractor notice to complete the work within a reasonable time, nor did he wait a reasonable time after a demand for completion. It is quite immaterial to a decision of the appeal whether the owner’s right to damages is to be determined by the contract or depends upon the actual damage which he sustained by the failure of the contractor to perform within the time specified; for he showed that his actual damages were greater th.an his liquidated damages, and he has not been allowed to recover either. Since, however, there must be a new trial, it is advisable that we express our views on the question of damages. We are of opinion that since the owner in effect canceled the contract, whether rightly or wrongly, and the contractor acquiesced therein, the contract no longer governs, and is to be resorted to only to determine how long plaintiff was in default in completing the work. In that view, the owner’s damages are limited to the period between the time when the contractor agreed to perform, and the time when
[5] We are of opinion, therefore, that the appellant was entitled to offset against the respondent’s claim the general damages which he sustained by the loss of the use of the building between the day when it was to be completed and the day appellant took charge of it in its uncompleted condition. This view necessarily requires a new trial; but in granting it it is proper to comment on some other claims with respect to the question of damage.
[6] The recovery by the respondent for brick and cement delivered on the premises by its subcontractor who claimed the same cannot be sustained on the evidence in this record, which does not present facts showing that title to the material passed to the respondent.
[7] It was, of course, proper for witnesses in forming their opinions with respect to the value of the work done by the respondent to include the actual cost of material and labor and a reasonable profit to the contractor; but the respondent was not entitled to recover for the separate items, and, although the evidence in chief was not confined to the reasonable value of the work as a whole, the learned referee undoubtedly followed the proper rule in finally estimating the damages in this regard.
[8] The plaintiff’s claim on the theory of a quantum meruit is necessarily unliquidated and incapable of determination by market values or an arithmetical calculation, and it was not entitled to recover interest. Delafield v. Village of Westfield, 41 App. Div. 24 , 58 N. Y. Supp. 277 ; Excelsior Terra Cotta Co. v. Harde, 181 N. Y. 11 , 73 N. E. 494 , 106 Am. St. Rep. 493 ; Coates v. Village of Nyack, 127 App. Div. 153 , 111 N. Y. Supp. 476 ; Fox v. Davidson, 111 App. Div. 174 , 97 N. Y. Supp. 603 ; Beckwith v. City of New York, 121 App. Div. 462 , 106 N. Y. Supp. 175 ; O’Reilly v. Mahoney, 123 App. Div. 275 , 108 N. Y. Supp. 53 .
It follows, therefore, that the judgment should be reversed, and a new trial granted before another referee, with costs to appellant to abide the event.
INGRAHAM, P. J„ and CEARKE and MILLER, JJ., concur. SCOTT, J., concurs in result.
Cases cited
- Wyckoff v. Taylor 13 App. Div. 240 p. 982
- Lawson v. Hogan 93 N. Y. 39 p. 982
- Simmons v. Ocean Causeway of Lawrence 21 App. Div. 30 at 47 p. 982
- Fraenkel v. Friedmann 199 N. Y. 351 p. 982
- Richard Deeves & Son v. Manhattan Life Insurance 195 N. Y. 324 p. 983
- Mosler Safe Co. v. Maiden Lane Safe Deposit Co. 199 N. Y. 479 p. 983
- Delafield v. Village of Westfield 41 App. Div. 24 at 58 p. 984
- Excelsior Terra Cotta Co. v. Harde 181 N. Y. 11 at 73 p. 984
- Beckwith v. City of New York 121 App. Div. 462 p. 984
- O'Reilly v. Mahoney 123 App. Div. 275 p. 984