Majority
Headnote
1. Mechanics’ Liens (§ 115[2] ) — Advance Payment to Avoid Lien Law— Requisite Peo of.The important question involved in this litigation, which was instituted to foreclose a mechanic’s lien, is whether the final payment by the owner to the contractor was made for the purpose of
“Any payment by the owner to a contractor upon a contract for the improvement of real property, made prior to the time when, by the terms of the contract such payment becomes due, for the purpose of avoiding the provisions of this article, shall be of no effect as against the lien of a subcontractor, laborer or materialman under such contract, created before such payment actually becomes due.”
The contract.in question was made in September, 1911, and provided for furnishing the materials an ; performing the labor necessary for the construction by the contractor, Booth, for the Schenectady County Coal Company, the appellant, of five reinforced concrete coal pockets, for the sum of $75,500, payments to be made monthly to the extent of 85 per cent. of. the architect’s estimates, the final payment to be made 31 days after the completion of the contract, which as to the large pocket was to be February 1, 1912, and as to the four small pockets, June 1, 1912. The contract provided that the owner might retain, out of any payments due or to become due, sufficient moneys to indemnify it against any liens chargeable to the contractor; also, that before final payment should be made, the contractor should furnish to the owner a bond in the penal sum of $18,750 conditioned that the contractor should keep all the buildings in repair for the period of one year from the time of their completion. Upon undertaking the construction of the large pocket it was found that the laying of a concrete mat as a foundation to the pocket was necessary. This was done at an expense of $7,209.36, which was paid for as extra work, and accounts for the delay in the completion of the contract, but has no bearing upon the issues herein. On March 8, 1912, the appellant had paid Booth on account of the contract, and exclusive of the payment for the extra work of constructing the mat, $55,505, leaving unpaid upon the contract $19,995. The appellant then proposed to Booth that, if he would furnish it a surety bond in the penalty of $20,000 conditioned for the performance by him of the contract, it would pay him, in advance of the time specified in the contract, the said balance remaining unpaid thereon. March 15, 1912, Booth in acceptance of such proposition furnished said bend, and on M trch 19th the appellant paid him $15,000, and on March 26th, the balance of $4,995 in full of the contract price, and also of the extra work in constructing the concrete mat. Booth continued work upon the pockets until June 13, 1912, when he abandoned the contract, and on June 17, 1912, became a bankrupt, having then expended upon the contract, exclusive of the construction of the mat, $79,960.64. The surety company thereupon undertook the work of completing the contract and expended $8,000 thereon. Thereafter the appellant, claiming that the surety company had not fully completed the contract, wliich claim the surety company disputed, expended $2,000 upon the pockets. Commencing June 18, 1912, plaintiff and many of the defendants filed liens against the coal pocket properties, and in July, 1912, this action was brought to fore-, close the lien of the respondent cement company.
The court in its decision, which is amply supported by the evidence, excepting in respect of the claim Of the respondent cement company,
[1, 2] The mere fact that the March payments were made to Booth in advance of the time required by the contract, or that the appellant had knowledge of the indebtedness of Booth to the lienors, is not of itself sufficient, under the present Lien Law, to charge the appellant with liability on account of such payments, but in addition thereto it must be shown, in order to avoid the effect of a payment as against a lien, that the advance payments were made for the purpose of avoiding the provisions of the Lien Law, and, the burden of so proving is upon the person asserting it. Behrer v. McMillan, 114 App. Div. 450 , 100 N. Y. Supp. 35 ; Tommasi v. Archibald, 114 App. Div. 838 , 100 N. Y. Supp. 367 ; Hudson River Stone Co. v. Huntington, 143 App. Div. 99 , 128 N. Y. Supp. 25 ; Wagner v. Butler, 155 App. Div. 425 , 140 N. Y. Supp. 50 .
“In taking up the matter further in relation to our telephone talk of a few days ago, I would like you to let me know how much cement as delivered to the Schenectady County Coal Company plants for Mr. Booth, you figure is unpaid for. I have of course, figured that while you hold notes for some of this cement, same is not really paid for until notes are paid; and also would like to ask if you are perfectly satisfied with Mr. Booth’s responsibility, and willing to waive all claims against the Schenectady County Coal Company in the future.”
So far as appears this letter was not answered. March 19, 1912, Ashton wrote Bayle the following letter:
“ (Personal)
“Mr. G. F. Bayle, President, Glens Falls Portland Cement Co., Glens Falls, N. Y. — Dear Sir: Confirming conversation over telephone this morning, we have" arranged to pay Mr. Booth in full for contract work at Schenectady, notwithstanding that contract is not completed. He is giving us a bond for the amount of money advanced. We gave him this morning a check for $15,000, which leaves a balance of $4,995. We will give him a check for this balance, within the next day or two.
“Yours very truly, E. B. Ashton.”
It was not until seven days later that the appellant made the final payment to Booth of $4,995. Ashton testified that the reason he wanted to let Bayle know that the appellant was to make final payment to Booth was because Bayle was a personal friend, and Ashton knew the cement company was furnishing all the cement for the construction of the pockets, and assumed that the cement company bill would be as large as any and was anxious that Bayle should know the situation, and what was going on. Booth was a large purchaser of cement, having other large contracts for concrete work, and was indebted to the cement company in a considerable sum, and evidently the cement company considered it better business to continue to furnish him cement and allow him to proceed with his contracts and take the chances of meeting with a loss, as Bayle told Ashton he thought Booth was good, than to endeavor to secure, by filing a lien, or enforce by action pay-' ment of his then indebtedness, as the cement company furnished him cement for his jobs up to the time he abandoned the contract, June 13, 1912; the amount furnished for the work upon the pockets being about $2,000. The cement company, however, received from Booth during that period payment of his note of $5,000.
Unquestionably at the time of making the final payment the officers
Dissent
The decisions of the trial court should be modified by reversing the decree as to the cement company and dismissing the complaint upon the merits with costs, and by affirming the decree as to the other respondent lienors with costs.
The court disapproves of findings Nos. 17 and 18 so far as they find that the payments of March 19th and 26th, aggregating $19,995, were made, as to the said cement company, for the purpose of avoiding the provisions of the Lien Law, and that the said cement company is entitled to be paid the amount of its said claim, and substitutes a finding that as to said cement company said payments made in advance were not made for the purpose of avoiding the provisions of the Lien Law, and that said cement company is not entitled to be paid, by appellant or to enforce its lien for any sum whatever. All concur, except KELLOGG, J., who writes for reversal in which WOODWARD, J., concurs.
(dissenting). The original contract price was $75,500, of-which 85 per cent, was to be paid on estimates of the architect from time to time as the work progressed and the remaining 15 per cent. ($11,350) was to be paid 30 days after the completion of the contract. In March, 1912, the work done (about two-thirds of the requirements of the contract) had cost $65,300. The payments to the contractor at that time aggregated $55,505, leaving apparently over $32,000.of work to be done by the contractor for which appellant was to pay $19,995. He was urging that more money be paid to enable him to continue the work, and .was apparently in embarrassed circumstances. It was agreed, in March, 1912, in order to facilitate the work and secure the completion of the contract, that the appellant would pay to him the balance of the contract price; he giving to appellant a surety bond for the completion of the work. The bond was given, the balance paid, and the contractor continued the work until June 13, 1912, when he abandoned it. The architect’s certificate shows that the cost of the work and material in place at that time was $83,300. The surety upon the bond was required to continue the work, and expended $8,000 thereon. The appellant spent $2,000 as 'it claims in the completion of the .contract after the surety claimed the contract was performed. The total cost of the work, therefore, was $90,300, or $92,300 if the amount expended by the owner is allowed. No attention has been paid to the extra work which was paid for and does not enter into this controversy. The plaintiff, a large creditor, was notified in advance that the advance payments were to be made unless it objected, and it apparently was willing to look to the contractor for its pay. Certainly as to it no question can arise as to the entire good faith of the appellant; the
Section 7 of the Lien Law is a reasonable provision and simply requires that the owner shall not accelerate payments for the purpose of defeating the liens which may be filed against the property. Where a payment is accelerated for good and sufficient reasons for the necessary protection of the owner, and only to the extent reasonably necessary for his protection, it cannot be claimed that such payment was made for the purpose of avoiding the provisions of the act. It is not material just how many dollars and cents were actually expended in completing the work; it was reasonably within the contemplation of the appellant at the time that the entire payments advanced by it would be necessary for the completion of the work. In so large a transaction where the figures so nearly approach each other there is no foundation for the claim that the act was prompted by any ulterior or improper purpose. The reasonable intendment of good faith is sufficient under the circumstances of this case to protect the payment made by the appellant. Had the Legislature intended that under no circumstances should the owner make payments to the contractor prior to their becoming due, it could have made the intent clear by saying so. It did .not do this, but provided that a payment made before it becomes due should be of no effect as against the subcontractor, laborer, or materialmen “if made for the purpose of avoiding the provisions of this article.” It would seem to follow that any payment made for any other legitimate purpose remains unaffected by the statute. The mere fact that the owner knows that a contractor is indebted to laborers, materialmen, or subcontractors is not sufficient to charge upon him an improper purpose in making the payments. When the evidence is all in, the payments must be allowed unless it appears that they were the result of a purpose to avoid the statute. If it appears that it was for the sole purpose of continuing the work atid enabling the contractor to perform his contract and was reasonably necessary therefor, the payment is valid. Wagner v. Butler, 155 App. Div. 425 , 140 N. Y. Supp. 50 ; Hudson River Blue Stone Co. v. Huntington, 143 App. Div. 99 , 128 N. Y. Supp. 25 .
I favor a reversal of the judgment.
WOODWARD, J., concurs.
Cases cited
- Behrer v. City & Suburban Homes Co. 114 App. Div. 450 p. 192
- Tommasi v. Bolger 114 App. Div. 838 p. 192
- Hudson River Blue Stone Co. v. Huntington 143 App. Div. 99 at 128 p. 192, p. 196
- Wagner v. Butler 155 App. Div. 425 p. 192, p. 196