Majority
Headnote
1. Contracts—Unforeseen Obstructions—Assumption of Risk.On January 14, 1893, the plaintiff entered into a contract with the defendant, whereby he agreed to “excavate, remove, and dispose of all silt, sediment, and other materials deposited in the bottom of the ‘Pond,’ near Fifty-Ninth street, Fifth and Sixth avenues, and construct a concrete bottom over same.” The work was accepted by the department of public parks on August 22, 1894; and on September 24, 1894, the plaintiff, in consideration of payments made to him, gave a general release of all claims arising under the contract, except a certain sum not material here, and (to quote) “any legal claim which I may have, if any, for extra work not covered by the contract herein.” In this action the plaintiff seeks to recover for certain work which he claims was not within the contract, and for which he has not been paid.
The principal item of the plaintiff’s claim is a bill for pumping. The facts concerning it are as follows: The pond had an outlet at one end, consisting of a circular gate 20 inches in diameter, resting on the bottom of the pond, and connecting with a branch sewer running into Fifty-Ninth street. There was also an overflow básin about 25 feet from the gate,- and 5 or 6 feet higher. In the course of the work, the outlet gate was opened, but the water ran off only to 12 or 14 inches from the bottom of the gate. This was due to an obstruction in the sewer. Plaintiff then had a conversation with the engineer in charge of the work for the defendant, who told him it
The plaintiff contends that it was the defendant’s duty to see to it that the outlet gate and sewer were in a state of good repair, and that he may recover for the extra work thrown upon him by its failure so to do. Admitting the premise, the conclusion seems properly to follow. It is settled law that a contractor may recover, upon a •quantum meruit, the value of extra and unnecessary work imposed upon him in the performance of his contract by an unjustifiable act or omission of the other party thereto. Messenger v. City of Buffalo, 21 N. Y. 196 ; Mansfield v. Railroad Co., 102 N. Y. 205 , 6 N. E. 386 ; Mulholland v. Mayor, etc., of New York, 113 N. Y. 631 , 20 N. E. 856 ; Del Genovese v. Railroad Co., 13 App. Div. 412 , 43 N. Y. Supp. 8 . The crucial question in the case, therefore, is whether the defendant was under a duty to the plaintiff to furnish him the outlet gate and sewer in good working order. To determine that question, we must ■examine the contract between the parties in the light of the surrounding circumstances. If such an examination shows that an agreement' ef this nature is fairly to be implied, the plaintiff is as much entitled to recover as though it were contained in the instrument in express words.
As was said by Allen, J., in Booth v. Mill Co., 74 N. Y. 15 , 21:
“There is no particular formula of words or technical phraseology necessary to the creation of an express obligation to do or forbear to do a particular thing or perform a specified act. If from the text of an agreement and the language of the parties, either in the body of the instrument or in the recitals •or references, there is manifested a clear intention that the parties shall do certain acts, courts will infer a covenant in the case of a sealed instrument, or a promise if the instrument is unsealed, for nonperformance of which an action of covenant or assumpsit will lie.”
But an examination of the contract leads us to believe that the defendant did not, expressly or by fair implication, assume any duty towards the plaintiff with reference to the outlet gate and sewer. Section 2 of the specifications provides that the compensation for, among other things, “all labor and materials required for conducting the flow of water through or across the area of the pond or any portion thereof, and all pumping or bailing or other work required, will be included in the price stipulated in this agreement for excavation.” Section 5 reads: “All labor and materials required for conducting the flow of water through or across the area of the ‘Pond’ to the outlet, or for draining water from any portion of the area, and all pumping or bailing required for the proper prosecution of the work during its progress, and until its completion, will be furnished by the contractor at his own cost and expense.” There seems to be here a plain provision that the plaintiff was not to receive any extra compensation for pumping work, if such work should prove necessary. If the outlet gate and sewer had been equal to draining all the water off the pond, no pumping would apparently have been required. The plaintiff would simply have had to dig drains to conduct the water to the gate. The insertion in the contract of a specific provision that,
The remainder of the plaintiff’s claim arises out of a dispute between himself and the engineer as to the amount of certain excavated material. In part the dispute seems to have been caused by a difference in the mode of computation, adopted by the two parties, and in part by a mere error of measurement on some one’s part. The details of the controversy are not material. Concededly, the work was not extra work, but work specifically provided for and covered by the contract. Any claim with regard thereto is consequently embraced in the general release given, by the plaintiff, which he made not the slightest offer or attempt to attack in any way.
The judgment should be affirmed, with costs. All concur.
Cases cited
- Messenger v. City of Buffalo 21 N. Y. 196 p. 581
- Mansfield v. New York Central & Hudson River Railroad 102 N. Y. 205 p. 581
- Mulholland v. Mayor of New York 113 N. Y. 631 p. 581
- Genovese v. Third Avenue Railroad 13 App. Div. 412 p. 581
- Booth v. Cleveland Rolling Mill Co. 74 N. Y. 15 at 21 p. 581
- Bonesteel v. Mayor 22 N. Y. 162 p. 582
- MacKnight Flintic Stone Co. v. Mayor of New York 13 App. Div. 231 p. 582