Majority
Headnote
1. Pleading—Admissions—Estoppel.The action is to foreclose a mechanic’s lien upon
certain funds in possession of the city of New York applicable to the payment of repairs to a public school. The city contracted with defendant Theriault to make the repairs for $1,895. Theriault subcontracted with the plaintiffs to do a portion of the work for $1,240. The plaintiffs performed all the work required by their subcontract. Theriault did not perform all the work required by his contract, but abandoned the same. The city then took charge of the work and caused it to be completed by another contractor. The city paid Theriault on account $595, and subsequently paid the other contractor $528 for completing the work, thus leaving $772 unpaid on the Theirault contract. Theriault paid the plaintiffs $500 on account of the work done under the Subcontract, and there remains due the plaintiffs for work performed under such subcontract the sum of $740.
The city of New York interposes many objections to the maintenance of this action.
First. It is urged that the action should have been brought against the board of education under the authority of Gunnison v. Board of
Second. It is claimed that, inasmuch as Theriault abandoned the contract, the contract thereby was forfeited, and the subcontractor cannot recover the unpaid balance. Provision Q of the contract authorizes the board of education to take possession of the work and complete the same upon abandonment, and to make the cost and expense of com.pletion a charge against the contractor. And the notice served upon the contractor was to the effect that the cost and expense of completing the contract would be charged against the contractor. Undei; such circumstances the contractor or subcontractor, as the case may be, may recover the balance due him, less the cost of completion. Holl v. Long, 34 Misc. Rep. 1 , 68 N. Y. Supp. 522 ; McKee v. Rapp (Super.) 35 N. Y. Supp. 175 ; New Jersey Steel & Iron Co. v. Robinson, 74 App. Div. 485 , 77 N. Y. Supp. 547 ; Crouch v. Gutmann, 134 N. Y. 45 , 31 N. E. 271 , 30 Am. St. Rep. 608 .
Third. It is urged that under clause W of the contract certificates of completion must be secured before the contractor becomes entitled to payment. Such certificates are waived when the owner completes, pursuant to the contract. Holl v. Long, supra.
Fourth. It is urged that under clause U the contractor, and therefore the subcontractor, is precluded from making any claim until all liens are removed. The provision is in substance that the contractor will not suffer or permit any lien “to be put or remain on the buildings or premises into or upon which any work is done or materials are furnished under this contract.” It is a sufficient answer to this objection to say that the lien filed for work done on public improvements is not a lien on the building or premises, but is a lien on the funds applicable to the payment of the work.
The fifth objection is that under section 13 of the lien law (Laws 1897, p. 520, c. 418) the notice of lien must be filed within 30 days after the completion and acceptance of the work by the municipal corporation, and that the work has never been completed by Theriault, and that the notice of lien was served more than 30 days after the time of the abandonment. It is conceded that the work was completed by the city through the aid of another contractor, and the work as so completed was accepted by the city. The work of completion was done at the expense of Theriault and for him, and the lien was filed before such completion, as permitted by section 13 of the lien law.
The next objection urged is that under clause Z of the contract Theriault was prohibited from assigning or subletting the contract. I doubt whether the letting out of a parton of the work to the plaintiffs was a violation of this clause of the contract. In any event, the only penalty provided by clause Z for such subletting was that the contract might,
The plaintiffs are entitled to a judgment of foreclosure of their lien and to the payment of the amount thereof, so far as the funds in the possession of the city applicable to the payment of the Theriault contract will satisfy the same, and to a judgment for any deficiency, with costs against the defendant Theriault.
Judgment accordingly.
Cases cited
- Gunnison v. Board of Education 176 N. Y. 11 at 68 p. 353
- Bell v. Mayor of New York 105 N. Y. 139 p. 353
- Hall v. Long 34 Misc. Rep. 1 at 68 p. 353
- Crouch v. Gutmann 134 N. Y. 45 p. 353