Majority
Headnote
1. Contract—Breach.A fair interpretation of the contract is that the defendant was to sell and deliver to the plaintiffs 5,000 barrels, more or less, of Ironclad cement, which the plaintiffs might require to fill their contracts with the railroad company at Amsterdam, Degraff, and Hoffmans. The deliveries were to be 500 barrels January 1, 1902, 300 barrels January 15th, and 250 barrels per week thereafter,
Plaintiffs having notified the defendant and he in turn the mill that five car loads of cement were not accepted, it was not unreasonable for the Glens Falls Company to refuse to send other cement until it was determined whether their cement would pass this inspector or not. The cement was in fact according to the contract and specifications, but as the Glens Falls Company was the only company making this particular cement, and it was the only cement of that kind,- if it was not to be accepted there was no use of sending on other installments. The contract being made with reference to this cement, the provisions therein for inspection excused the plaintiffs from taking the cement unless it passed inspection, and if it did not pass inspection and was the regular product of that mill it probably excused the defendant. The failure to pass inspection was a contingency which both parties had in mind as possible, and if it failed there was probably no further liability of either party upon the contract for cement not already delivered. Dolan v. Rodgers, 149 N. Y 489 , 44 N.
It is clear that the plaintiffs refused to receive the 250 barrels of cement a week, as required by the contract, and in that respect broke the contract and became in default and liable to the defendant for any damage he might sustain thereby. It is undoubtedly the rule of law that one party to a contract cannot recover against the other so long as he himself is in default. Bonesteel v. Mayor, 22 N. Y. 162 , 170; Windmuller v. Pope, 107 N. Y. 674 , 14 N. E. 436 .
But the plaintiffs claim that the defendant, by furnishing cement from time.to time after March nth, thereby extended the terms of the contract, and, beginning from that time, was required to furnish the 250 barrels of cement per week until it was all delivered. We do not find any such agreement, and it would practically require a new contract to have that effect. Clark v. Fey, 121 N. Y. 470 , 24 N. E. 703 .
The only thing that can be claimed as tending to show any such understanding is that the plaintiffs ordered cement from time to time and the defendant filled the orders. But it is to be observed that these orders have no particular reference to the weekly installments mentioned in the contract, but were evidently given for such amounts as the plaintiffs needed. There is some evidence that the defendant stated he considered the contract was still binding, but those statements were made after the defendant’s inability to deliver the cement had been demonstrated, and not while the cement was being ordered by plaintiffs and furnished by defendant.
Where one party to a contract requests delay, he cannot defend against the other party because it was granted him. He is estopped from so doing. But here the defendant did not request the delay, and there is no estoppel against him. Thomson v. Poor, 147 N. Y. 402 , 410, 42 N.
Notwithstanding the vendor’s subsequent delivery of certain installments, it is probable that he might still recover any legal damages he sustained by the vendee’s refusing the goods at the time mentioned in the contract. Phillips & C. C. Co. v. Seymour, 91 U. S. 646 , 23 L. Ed. 341 ; Brady v. Cassidy, 145 N. Y. 171 , 180, 39 N. E. 814 ; Parke v. Franco-American T. Co., 120 N. Y. 51 , 56, 23 N. E. 996 .
Permitting performance after the time does not extend the time, but waives a complete performance. The party not in default may, nevertheless, terminate the contract or suffer it to go on and claim damages. Wyckoff v. Taylor, 13 App. Div. 240 , 43 N. Y. Supp. 31 .
The performance of the contract, according to its terms, having been prevented by the plaintiffs, the most favorable view to them is that the defendant had a reasonable time after request in which to fulfill, if he were still willing to go on with it, and such reasonable time depends upon all the surrounding circumstances. Simmons v. Ocean Causeway, 21 App. Div. 30 , 47 N. Y. Supp. 360 , and cases cited. Under that rule, the defendant being required to furnish a particular brand of cement which could only be made at one mill, and it being conceded that he used every effort he possibly could to obtain it for the plaintiffs, and it appearing that when the plaintiffs required the cement the mill was unable to furnish it, the defendant should not be held liable for failing to furnish the cement as requested. A plaintiff cannot recover in an action against another for breach of contract, except upon showing that he had performed, or is ready to perform; and if it appears that he, directly or indirectly, prevented the other party from performing, and the default of the other party is primarily due to the act or neglect of plaintiff, then no recovery can be had, but the party prevented from performing in full may recover pro rata. Otherwise the plaintiff would recover the damages flowing from his own acts. Vandegrift v. Cowles Engineering Co., 161 N. Y. 435 , 443, 55 N. E. 941 , 48 L. R. A. 685 ; Dolan v. Rodgers, 149 N. Y. 489 , 44 N. E. 167 .
After the tests were over and the cement accepted, a large amount was delivered in August. The last cash payment made by the plaintiffs was June 13th. That did not include the five car loads which the inspector did not pass and as to which the tests were made. So that in the deal between the parties these five car loads and the cement delivered in August was not paid for, and at the time the plaintiffs notified the defendant that they would not accept more cement, and treated him as violating the contract, they were indebted to the plaintiffs in a large amount for cement previously delivered. The con
It therefore clearly appears that upon any theory of the case, while the defendant was concededly making deliveries as required, the-plaintiffs were indebted to him and still remain indebted to him for cement previously delivered, and in fact several days before the plaintiffs notified the defendant of their termination of the contract for his nonperformance the defendant had demanded $i,coo of them, upon account, which was due them and has not been paid.
The plaintiffs, therefore, made the first default in this contract by refusing to accept the cement as provided for by the contract, and such default must prevent a recovery here by them. The defendant having delivered cement, as requested, to the plaintiffs who are in default, is entitled to recover for the cement actually delivered. Aside from the plaintiffs’ first default, they failed to pay for different lots of cement as soon as inspected. The defendant is entitled, therefore, to recover judgment upon his counterclaim for $1,303.57, with interest and costs.
Judgment for defendant, with costs.
Cases cited
- Dolan v. Rodgers 149 N. Y 489 p. 265, p. 267
- Bonesteel v. Mayor 22 N. Y. 162 at 170 p. 266
- Windmuller v. Pope 107 N. Y. 674 p. 266
- Clark v. Fey 121 N. Y. 470 p. 266
- Thomson v. Poor 147 N. Y. 402 at 410, 42 p. 266
- Bailey v. Western Vermont Railroad 18 Barb. 112 p. 267
- Phillips & Colby Construction Co. v. Seymour 91 U. S. 646 p. 267
- Brady v. Cassidy 145 N. Y. 171 at 180, 39 p. 267
- Parke v. Franco-American Trading Co. 120 N. Y. 51 at 56, 23 p. 267
- Wyckoff v. Taylor 13 App. Div. 240 p. 267
- Simmons v. Ocean Causeway of Lawrence 21 App. Div. 30 at 47 p. 267
- Vandegrift v. Cowles Engineering Co. 161 N. Y. 435 at 443, 55 p. 267